Offshore Wind farms in India

India has 17 offshore wind farm projects of which none currently operating, none where construction has progressed enough to connect the turbines and generate electricity, none are in the build phase, and none are either consented or have applied for consent. You can access over 80 data sets on each wind farm subject to your access level and drill down to see items such as:

on project 'First 1000 MW commercial offshore wind farm in India' on Tuesday, 31 March 2020, the following was announced: 'Update 23/11/2019: First tender postponed to March 2020; NIWE expresses need to complete environmental, geophysical and geotechnical assessments correctly before project can be tendered. NIWE recommends 4x250 MW, 2 x 500 MW or 1 x 1 GW tender.

Update (24/06/19): The expectation is that the 1 GW Gujarat tender will be out around October/November, however further delays are anticipated.

Update: tender process delayed and pushed back to 2019. A general election is to be held April-May 2019 but MNRE intend to still put out a tender during late Q1. As of May 2019 there is still no announcement,

Tendering of project scheduled for second half of 2018.'

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Copyright © 4C Offshore 2019

  • ISO 14001 173953 2015 AHSO GBR UKAS 2 | 4C Offshore
  • Achilles UVDB Supply Chain Community | 4C Offshore