BOEM publishes draft EIS for Rhode Island wind farm

4C Offshore | Tom Russell
By: Tom Russell 30/08/2022 BOEM

The Bureau of Ocean Energy and Management (BOEM) announced the availability of the Draft Environmental Impact Statement (DEIS) for the proposed
Revolution Wind energy project offshore Rhode Island.

The Notice of Availability for the Revolution Wind environmental analysis will publish in the Federal Register on 2 September opening a 45-day public comment period that ends at 11:59 p.m. ET on 17 October 2022. The input received via this process will inform preparation of the Final EIS.


“Collaborating with all stakeholders and ocean users throughout the leasing and development process is vital,” said BOEM Director Amanda Lefton. “We’re committed to maintaining open and transparent communication with all stakeholders, and value public input. BOEM is using the best available science as well as knowledge from ocean users and other stakeholders to avoid and minimize conflict with existing uses and marine life.”


Revolution Wind, LLC submitted a Construction and Operation Plan (COP) for its proposed wind farm of up to 100 wind turbines located approximately 15 nautical miles southeast of Point Judith, Rhode Island. The array, with an estimated capacity of between 704 to 880 MW, is expected to power at least 300,000 homes. The DEIS analyses the potential environmental impacts of the project as described in the COP and several alternatives to the proposed action.


BOEM will use the findings of the EIS to inform its decision on whether to approve Revolution Wind’s COP, and if so, what mitigation measures to require.


During the comment period, BOEM will hold three in-person and two virtual public meetings, where the public can learn more about: the review process, the EIS schedule, potential impacts from the proposed project, and proposals to reduce potential impacts.


For more information on offshore wind farms worldwide, click here.

Premium

4C Offshore Premium, our most popular subscription, gives you full access to use the 4C Offshore WebApp which includes exclusive offshore wind, transmission and vessel reports, news and downloads.

Request a 30 minute Demo

Trending News!