Installation continues for Hollandse Kust West Alpha's second subsea cable

4C Offshore | Chloe Emanuel
By: Chloe Emanuel 20/04/2023 TenneT

Contractor Jan de Nul continues to install the remaining section of second TenneT sea cable for the Hollandse Kust West Alpha project.

With over 60 kilometres of sea cable on board, the cable-laying vessel
Isaac Newton will appear off the coast of Heemskerk/Wijk aan Zee this week. With this cable section, the contractor combination Jan de Nul Group/LS Cable & System is realising the second connection for the offshore wind farm Hollandse Kust (west Alpha) to TenneT's 'socket at sea', 50 kilometres off the coast of Egmond aan Zee. The first sea cable connection for this wind farm was completed earlier this year.

About five kilometres from the beach, Jan de Nul will bring the first part of the second cable for 'west Alpha' to the surface. This cable was already pulled under the dunes last year, after which the first kilometres were laid in the seabed. On board the Isaac Newton, the end (currently still capped) will be connected to the cable on board by means of a so-called sleeve connection.

Once the connection has been made, the cable is placed back on the seabed. At the same time, the work vessel Symphony from the Belgian contractor's fleet appears off the coast. On board is the unmanned cable-laying vehicle Swordfish. Once the Isaac Newton sets sail, the sea cable will slowly unwind from the large turntable on board. The Symphony sails behind it to control the Swordfish, which then lays the cable into the seabed.

The cable is installed up to the site where TenneT is having the offshore transformer platform built for the Hollandse Kust West Alpha project. For this, at a distance of some 50 kilometres off the coast of Egmond aan Zee, the undercarriage is already on the seabed. This summer, the ready made superstructure will be placed on top of it. Through this grid connection, TenneT will soon bring energy from the sea to land.

The Hollandse Kust West Alpha wind farm, which will be realised and operated by Ecowende (a joint venture between Shell and Eneco), will soon consist of 54 wind turbines with a combined capacity of 756 MW. This is enough renewable energy to meet about 3% of the current Dutch electricity demand, corresponding to the consumption of one million households. The wind farm is expected to be fully operational by 2026.


For more information on installation and maintenance of major offshore wind farm components, click here.

Premium

4C Offshore Premium, our most popular subscription, gives you full access to use the 4C Offshore WebApp which includes exclusive offshore wind, transmission and vessel reports, news and downloads.

Request a 30 minute Demo

Trending News!