Subscribers only field |
Subscribers only field |
Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Array Cable |
Two failure occured at array cable G15 and F15 at ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Array Cable |
Jonathan Duffy, General Manager of London Array, s... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Array Cable |
Jonathan Duffy, General Manager of London Array, s... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Performance Monitoring |
In the period of April 2014 to March 2015 the offs... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Other |
Onshore substation work finished.... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Generating Power |
The project is still under construction but some o... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Turbine Installation |
151 of the 175 turbines have been installed to dat... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Export Cable Installation |
Stemat Spirit completed installation of the third ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine |
Jack up vessel SEA WORKER arrived on site to suppo... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Final Testing |
Construction Update: The latest installed turbines... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
|
Masdar Energy UK refinanced its 20% stake in the ... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Turbine Installation |
The first turbine was installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Turbine |
Jack up vessel SEA CHALLENGER conducted jack up an... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Offshore Substation |
Installation of the foundation for Substation 2 to... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Array Cable Installation |
The final array cable was installed at the site by... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Export Cable Installation |
Stemat Spirit began installation of the third expo... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Array Cable |
London Array Ltd submitted an pre-emptive applicat... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Cable |
Leask Marine completed work on the cabling, using ... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Other Approval |
London Array ltd. has been granted a marine licens... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Turbine Installation |
At this point, 46 turbines had been installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Turbine |
Remedial works is required at a number of turbines... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Turbine Installation |
Turbine installation started before the end of Dec... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Export Cable Installation |
Export cable installation vessel Stemat Spirit had... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Foundation Installation |
The final transition piece has been installed by S... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Other |
4 turbines and 15 array cables installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Array Cable |
The vessel Stemat 82 arrived at the site to conduc... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Export Cable Installation |
Stemat Spirit completed installation of the second... Subscribers only field |
Subscribers only field
|
Freemium Only 2006 |
Consent Authorised |
Principal cause for delays: Birds (red-throated di... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
|
Ofgem issued its decision regarding the circuit br... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Array Cable |
Stemat-82 will be conducting inter array cable re... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine |
Crew transfer vessels: SC Amethyst, SC Falcon, TMS... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Export Cable |
Spectrum 1 will be undertaking survey operations w... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Turbine |
Ziton vessel J/U WIND SERVER was on site supportin... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Turbine |
The jack up vessel J/U WIND was on site supporting... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Turbine |
J/U WIND SERVER was on the site supporting heavy m... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Export Cable |
Remedial work was carried out on the cables and ca... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Array Cable |
Stemat-82 conducted inter array cable repairs on c... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Cable |
Subsea cable installation and diving works started... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Other Application Submitted |
Following the failure of four array cables within ... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Export Cable Installation |
The fourth and final export cable was completed by... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Other |
70 monopiles and transition pieces had been instal... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Turbine Installation |
Up date: 133 of 175 foundation monopile and transi... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Offshore Substation |
Installation of the topside for Substation 1 took ... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Turbine Installation |
The final turbine was installed on 13 December. 5... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Offshore Substation |
Installation of the foundation for Substation 1 to... Subscribers only field |
Subscribers only field
|
Freemium Only 2009 |
Financial Close |
First phase of the project was given the go ahead.... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Other |
Red7Marine completed 6 months of diving work at Lo... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Turbine |
Ziton Wind Server arrived on site on behalf of SGR... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Financing Agreement |
Statkraft signed a Power Purchase Agreement (PPA) ... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Foundation Installation |
To date, 69 turbines and 139 foundations had been ... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Other |
Between 9th and 16th September 2016 the wind farm ... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Other |
175/175 monopiles installed, 117/175 turbines inst... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Other Application Submitted |
London Array ltd. submitted a marine license appli... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Other |
The Operations and Maintenance (O&M) base at Port ... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Offshore Substation |
Installation of the topside for Substation 2 was c... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Other |
Construction Update: 171 of 175 Turbines installed... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Foundation Installation |
The first foundation was installed by SEAWORKER.... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Generating Power |
141 of 175 turbines are now able to produce power ... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Turbine Installation |
The 100th turbine was installed leaving 75 turbine... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Turbine |
Jack up vessel SEA WORKER arrived on site to carry... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Turbine |
Jack up vessel SEA CHALLENGER was on supporting he... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Turbine |
On behalf of Siemens Gamesa MPI Adventure and Voss... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Array Cable |
update: The Bokabarge 82 is due to started on 6th ... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Turbine Service Agreement Expires |
The five-year OEM service agreement will expire.... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Fully Commissioned |
The 175th and final turbine was commissioned. The ... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Export Cable Installation |
Stemat Spirit began installation of the fouth expo... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Environmental and Seabed Monitoring |
MTS Xplorer started bathemetric surveys. The surve... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Turbine |
MPI Adventure departed site. This vessel was under... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Export Cable Installation |
Stemat Spirit began installation of the second exp... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Array Cable |
Remedial works on the array cables started. Work i... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
|
Van Oord completed the acquisition of MPI Offshore... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Other |
The Kentish Flats Extension project will be laying... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Generating Power |
First power generated in October 2012. The first t... Subscribers only field |
Subscribers only field
|
Freemium Only 2005 |
Consent Application Submitted |
Consent application was submitted.... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Turbine |
MPI Offshore had completed blade upgrades at 74 tu... Subscribers only field |
Subscribers only field
|
Freemium Only 2010 |
Onshore Construction Starts |
Onshore substation work started.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Array Cable Installation |
Array cable installation started in July 2011.... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Foundation Installation |
94 foundations (92 turbines and 2 substations) had... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Other Approval |
The Marine Management Organisation have granted th... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Performance Monitoring |
London Array set a new record for the amount of cl... Subscribers only field |
Subscribers only field
|
Freemium Only 2004 |
Met Mast/LiDAR |
Carl C A/S 68m Series 16 met mast installed by Sea... Subscribers only field |
Subscribers only field
|
Freemium Only 2008 |
Geotechnical Site Investigation |
Geophysical and geotechnical surveys were conducte... Subscribers only field |
Subscribers only field
|