Events on Hydropower Rudong Offshore Wind Farm (intertidal) 100MW demonstration project - phase 2

Location:
Status:
Fully Commissioned
Capacity:
80MW
4C Offshore | Location Map: Lat(32.609) Lon(121.007)

As an Offshore Wind Farm Subscriber, you can follow this project to add it to your dashboard.

How does the database work?

4C Offshore marine intelligence software provides you with exclusive access to a range of specialised services including the Global Offshore Wind Farm Database. 4C Offshore grants you exclusive access to online and offline databases, reports, newsletters, online tools and more.

There are three levels of access: Free, Freemium and Full. Freemium allows you to personalise notifications, use the search function and access more data.

You will need Full access to use the 4C Offshore interactive system, access reports, updates, news, downloads and more. To find out more about how 4C Offshore software works and the benefits of Full access, enquire below.

Sign up to Freemium Enquire about 4C Offshore

Events overview for Hydropower Rudong Offshore Wind Farm (intertidal) 100MW demonstration project - phase 2

Event Date Event Type Event

Description

Event Source

Subscribers Only

Subscribers Only

Event Date:

Subscribers Only

Event Type:

Subscribers Only

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2015 Generating Power

Event Date: Freemium Only 2015

Event Type: Generating Power

22 turbines connected to grid, amounting to 55MW's...

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2015 Turbine

Event Date: Freemium Only 2015

Event Type: Turbine

22 turbines were installed....

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2015 Turbine

Event Date: Freemium Only 2015

Event Type: Turbine

13 turbines were installed....

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2015 Other

Event Date: Freemium Only 2015

Event Type: Other

Problem of scour around foundations....

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2015 Turbine

Event Date: Freemium Only 2015

Event Type: Turbine

5 turbines installed....

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2015 Foundation

Event Date: Freemium Only 2015

Event Type: Foundation

Completion of 12 Jackets and 20 concrete foundatio...

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2015 Turbine

Event Date: Freemium Only 2015

Event Type: Turbine

Start of turbine installation....

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2014 Foundation

Event Date: Freemium Only 2014

Event Type: Foundation

Offshore construction starts, beginning with high-...

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2014 Other Approval

Event Date: Freemium Only 2014

Event Type: Other Approval

Project in "national offshore wind power developme...

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2014 Procurement Process (Supply Chain)

Event Date: Freemium Only 2014

Event Type: Procurement Process (Supply Chain)

Wind turbine step-up transformer, 35kV high voltag...

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2014 Engineering

Event Date: Freemium Only 2014

Event Type: Engineering

Call for tender to test five-pile jacket foundatio...

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2013 Procurement Process (Supply Chain)

Event Date: Freemium Only 2013

Event Type: Procurement Process (Supply Chain)

Phase II wind turbine tender started....

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2012 Onshore Construction Starts

Event Date: Freemium Only 2012

Event Type: Onshore Construction Starts

Civil construction started....

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2011 Site Investigation

Event Date: Freemium Only 2011

Event Type: Site Investigation

Passed the environmental investigation....

Subscribers Only

Source:

Subscribers Only

Subscribers Only

Freemium Only 2011 Site Exclusivity

Event Date: Freemium Only 2011

Event Type: Site Exclusivity

Passed the environmental investigation....

Subscribers Only

Source:

Subscribers Only

Subscribers Only