Denmark 406.7MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Horns Rev 3

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2020 Turbine Jack up vessel Wind Enterprise arrived to support ... Subscribers only field Subscribers only field
Freemium Only 2020 Turbine M/V Enterprise arrived on site to provide heavy ma... Subscribers only field Subscribers only field
Freemium Only 2020 The agreement with the authorities states that the... Subscribers only field Subscribers only field
Freemium Only 2019 Other 3 of the turbines were not connected to the substa... Subscribers only field Subscribers only field
Freemium Only 2019 Fully Commissioned On 22nd August, the Crown Prince of Denmark inaugu... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation The final  V164-8.3 MW turbine was installed. Inst... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement The last turbine destined for Horns Rev 3 was load... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation Update 22/11/2018: Due to delays, only 41 turbines... Subscribers only field Subscribers only field
Freemium Only 2018 Generating Power The windfarm started delivering power to Danish gr... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation Array cable installation completed for 11 turbines... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation The final transition piece has been installed... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation Approximately half of the turbines have been insta... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation The last transition pieces have left Esbjerg Port ... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation Last four transition pieces were loaded onto the v... Subscribers only field Subscribers only field
Freemium Only 2018 Other Approval The Danish Energy Agency announced that the proje... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable On the 8th - 9th of August, vessel Vina completed ... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation The first turbine was installed by Brave Tern.This... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation Vole au vent arrived in Vlissingen to load the fir... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement Brave Tern is mobilising in the Port of Esbjerg to... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement From early July SAL will begin transporting 49 tra... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement The first nacelle with the new logo has arrived at... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement Smulders Projects Belgium NV chosen by GeoSea and ... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation DP2 Innovation has left site after installing all ... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation DP2 Innovation is on site and has commenced instal... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement Monopiles will be loaded into installation vessel ... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement First monopiles are ready to be shipped from the P... Subscribers only field Subscribers only field
Freemium Only 2017 DONG Energy and Vattenfall secured an agreement on... Subscribers only field Subscribers only field
Freemium Only 2017 Construction - Seabed Preparation Laying of erosion protection on the seabed where t... Subscribers only field Subscribers only field
Freemium Only 2017 The Port of Esbjerg are currently preparing the sh... Subscribers only field Subscribers only field
Freemium Only 2017 Grid Connection Available It is guaranteed a grid connection will be availab... Subscribers only field Subscribers only field
Freemium Only 2016 Offshore Substation The vessel SEA INSTALLER transported the transform... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation JD-Contractor completed the burial of the entire 3... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation JD-Contractor pulled in the export cable.
Due to... Subscribers only field
Subscribers only field
Freemium Only 2016 Export Cable Installation The vessel Topaz Installer arrived at the offshore... Subscribers only field Subscribers only field
Freemium Only 2016 Financial Close Vattenfall has taken the decision to invest in the... Subscribers only field Subscribers only field
Freemium Only 2016 Offshore Substation The substation topside was installed at the site.... Subscribers only field Subscribers only field
Freemium Only 2016 Offshore Substation The vessel Stanislav Yudin returned to the site to... Subscribers only field Subscribers only field
Freemium Only 2016 Offshore Substation The vessel Stanislav Yudin left the site after ins... Subscribers only field Subscribers only field
Freemium Only 2016 Offshore Substation The heavy lift vessel Stanislav Yudin installed th... Subscribers only field Subscribers only field
Freemium Only 2016 Offshore Substation The heavy lift vessel Stanislav Yudin arrived on s... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Roll off of HRC substation. Substation will now be... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement In the early hours the jacket foundation set sail ... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Load out of the 1600 ton substation foundation ont... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Hollandia Offshore has installed the sling platfor... Subscribers only field Subscribers only field
Freemium Only 2015 Tender Process Vattenfall awarded the tender for offshore turbine... Subscribers only field Subscribers only field
Freemium Only 2015 Other The last land cable was pulled in. This 220kv land... Subscribers only field Subscribers only field
Freemium Only 2015 Subsidy/PPA Conditionally Secured Vattenfall was awarded the concession to build and... Subscribers only field Subscribers only field
Freemium Only 2015 Tender Process The deadline for the best and final offer was Febr... Subscribers only field Subscribers only field
Freemium Only 2014 Tender Process The final tender conditions were published on the ... Subscribers only field Subscribers only field
Freemium Only 2014 Other Approval The Nature Agency has given EIA approval and issue... Subscribers only field Subscribers only field
Freemium Only 2014 Other Application Submitted Deadline to submit preliminary bids. After this, n... Subscribers only field Subscribers only field
Freemium Only 2014 Tender Process The invitation to tender has started for the four ... Subscribers only field Subscribers only field
Freemium Only 2014 Site Investigation The results of the Environmental Impact Assessment... Subscribers only field Subscribers only field
Freemium Only 2014 Tender Process All four of the applicants who applied for prequal... Subscribers only field Subscribers only field
Freemium Only 2014 Tender Process Deadline for applications for pre-qualification. F... Subscribers only field Subscribers only field
Freemium Only 2014 Site Investigation Between 27/02/2014 and 01/03/2014 5 magnetic anoma... Subscribers only field Subscribers only field
Freemium Only 2014 Tender Process Vattenfall have released a call for bids for an 'I... Subscribers only field Subscribers only field
Freemium Only 2014 Tender Process Vattenfall have released a call for bids for a 'Wi... Subscribers only field Subscribers only field
Freemium Only 2014 Tender Process Vattenfall have released a call for bids for a 'Fo... Subscribers only field Subscribers only field
Freemium Only 2013 Tender Process The notice for tender was published and the best p... Subscribers only field Subscribers only field
Freemium Only 2013 Site Investigation The geotechnical survey results are scheduled to b... Subscribers only field Subscribers only field
Freemium Only 2013 Tender Process Tender for detailed design work of the substation ... Subscribers only field Subscribers only field
Freemium Only 2013 Site Investigation The geophysical data was completed. The area surve... Subscribers only field Subscribers only field
Freemium Only 2013 Geotechnical Site Investigation The results of the geophysical surveys were publis... Subscribers only field Subscribers only field
Freemium Only 2013 Site Investigation Presentation of results of geophysical and geotech... Subscribers only field Subscribers only field
Freemium Only 2013 Geotechnical Site Investigation Geotechnical investigations were scheduled for 201... Subscribers only field Subscribers only field
Freemium Only 2012 Tender Process The Danish Energy Agency has appointed Energinet.d... Subscribers only field Subscribers only field
Freemium Only 2012 Other Approval The Danish government has agreed to proceed with a... Subscribers only field Subscribers only field
Freemium Only 2011 Feasibility Study Update to "Fremtidens Havmølleplaceringer - 2025" ... Subscribers only field Subscribers only field
Freemium Only 2007 Feasibility Study "Fremtidens Havmølleplaceringer - 2025" released, ... Subscribers only field Subscribers only field