Germany 288MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for DanTysk

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Service Agreement Expires Vattenfall has awarded Siemens Gamesa a one year n... Subscribers only field Subscribers only field
Freemium Only 2020 Tender Process Vattenfall has issued a tender for provision of 70... Subscribers only field Subscribers only field
Freemium Only 2020 Turbine Service Agreement Expires The turbine Service and Availability Agreement (SA... Subscribers only field Subscribers only field
Freemium Only 2020 Offshore Substation Bakker Sliedricht reports completion of works at t... Subscribers only field Subscribers only field
Freemium Only 2020 Turbine Service Agreement Expires The five-year OEM service agreement will expire.... Subscribers only field Subscribers only field
Freemium Only 2019 Offshore Substation Partial shutdown of the Sylwin 1 converter station... Subscribers only field Subscribers only field
Freemium Only 2019 Onshore Substation Shutdown of the full 864 MW capacity at the Sylwin... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine J/U WIND SERVER was on site supporting maintenance... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Seajacks Hydra arrived on the site to carry out ma... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine J/U WIND SERVER returned to the site for maintenan... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine J/U WIND SERVER was on site for maintenance work.... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine J/U WIND SERVER was back on site for maintenance w... Subscribers only field Subscribers only field
Freemium Only 2017 Cable Framework Agreement The framework agreement between JD Contractors and... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Ziton vessel J/U WIND SERVER arrived on site to ca... Subscribers only field Subscribers only field
Freemium Only 2016 Other The 2500 tonne topside of the accommodation platfo... Subscribers only field Subscribers only field
Freemium Only 2016 Other The 1300 tonne jacket for the accommodation platfo... Subscribers only field Subscribers only field
Freemium Only 2016 Fitting out of accommodation platform continues wi... Subscribers only field Subscribers only field
Freemium Only 2015 Production and Procurement The accommodation platform completed its journey f... Subscribers only field Subscribers only field
Freemium Only 2015 Fully Commissioned Official commissioning occured. The ceremony was a... Subscribers only field Subscribers only field
Freemium Only 2015 Generating Power It is believed that project is running at full cap... Subscribers only field Subscribers only field
Freemium Only 2014 Generating Power Trial operations for exporting 288MW of power to s... Subscribers only field Subscribers only field
Freemium Only 2014 Generating Power Vattenfall reported that DanTysk is successfully g... Subscribers only field Subscribers only field
Freemium Only 2014 Generating Power DanTysk was ready to undergo trial operations; the... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation Turbine installation has been completed with the 8... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation The 56th turbine was installed at the project. Thi... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation Turbine installation reached the halfway mark. Eac... Subscribers only field Subscribers only field
Freemium Only 2014 Generating Power By this point around 140MW of power had been conne... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation Over half of the array cables were installed. This... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation Three turbines were installed at locations DT69, D... Subscribers only field Subscribers only field
Freemium Only 2014 Offshore Substation The offshore substation is at the end of its commi... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation The first turbine, of 80, was installed.... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation After some delays the turbine installation started... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation Turbine installation started with the first tower ... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation Installation of the remaining array cables commenc... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation VSMC has now stepped in to take over array cable i... Subscribers only field Subscribers only field
Freemium Only 2014 Other No vessels have entered the site since 13/12/2013.... Subscribers only field Subscribers only field
Freemium Only 2013 Other Turbine delivery and preassembly increased in Dece... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation On this date Project Director Ole Bigum-Nielsen st... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation Installation on the array cables took longer than ... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Monopile installation was completed with all 80 mo... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Turbine installation was initially scheduled to be... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Approximately 70 foundations had been installed, l... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation Van Oord array cable installation vessels Jan Stee... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Construction Update: 45 foundations were installed... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation In total 40 of 80 foundations had been installed a... Subscribers only field Subscribers only field
Freemium Only 2013 Offshore Substation The offshore substation was installed on this day.... Subscribers only field Subscribers only field
Freemium Only 2013 Offshore Substation Substation has been loaded out, with installation ... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation The first array cable has been laid between founda... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Construction Update: 20 foundations and 20 transit... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 14 monopiles and 5 transition pieces had been inst... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation The first transition piece (TP) was installed. The... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation The Seafox 5 had installed 8 foundations at the si... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation The first monopile of 80 was installed by the Seaf... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation The first monopiles travelled to the site. During ... Subscribers only field Subscribers only field
Freemium Only 2012 Construction - Seabed Preparation Scour protection started in November 2012. Van Oor... Subscribers only field Subscribers only field
Freemium Only 2012 Other The installation vessel, the Seafox 5 arrived in R... Subscribers only field Subscribers only field
Freemium Only 2012 Other Foundation deliveries started at BOW Terminal. 40 ... Subscribers only field Subscribers only field
Freemium Only 2012 Onshore Construction Starts First construction work on the turbine elements be... Subscribers only field Subscribers only field
Freemium Only 2011 Grid Connection Agreed Unconditional grid offer in place with TenneT .... Subscribers only field Subscribers only field
Freemium Only 2010 Financial Close Final Investment Decision was made for DanTysk in ... Subscribers only field Subscribers only field
Freemium Only 2009 Tender Process In August 2009 Vattenfall invited tenders for the ... Subscribers only field Subscribers only field
Freemium Only 2009 Geotechnical Site Investigation Geotechnical site surveys carried out at all sites... Subscribers only field Subscribers only field
Freemium Only 2005 Consent Authorised Consent authorisation was given by the Federal Mar... Subscribers only field Subscribers only field