Germany 295.2MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Nordsee Ost

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2024 Corporate PPA Secured On 9th September 2019, Deutsche Bahn signed an agr... Subscribers only field Subscribers only field
Freemium Only 2022 Turbine Service Agreement Expires Senvion's OEM long-term service contract will expi... Subscribers only field Subscribers only field
Freemium Only 2020 Turbine Service Agreement Expires OMM's 5 year cable repair and maintenance contract... Subscribers only field Subscribers only field
Freemium Only 2019 Offshore Substation Partial shutdown of Helwin 1 converter station due... Subscribers only field Subscribers only field
Freemium Only 2019 Onshore Substation Shutdown of the full 576 MW capacity at the Helwin... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine On behalf of Senvion, Geosea's Neptune was on site... Subscribers only field Subscribers only field
Freemium Only 2018 Kvaerner and Innogy are still in dispute over the ... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Neptune arrived on site to provide heavy maintenan... Subscribers only field Subscribers only field
Freemium Only 2017 Health and Safety A fire broke out in the engine room of the wind fa... Subscribers only field Subscribers only field
Freemium Only 2017 innogy placed the first German corporate Green Bon... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Senvion carried out maintenance work using jack up... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine DP2 THOR carried out heavy maintenance work on the... Subscribers only field Subscribers only field
Freemium Only 2016 Other Approval DNV GL awarded innogy SE with the project certific... Subscribers only field Subscribers only field
Freemium Only 2016 Performance Monitoring Nordsee Ost has fed 1TWh into the grid since it be... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Jack up vessel Neptune supported turbine maintenan... Subscribers only field Subscribers only field
Freemium Only 2015 Performance Monitoring Due to strong winds of up to 27m/s, the wind farm ... Subscribers only field Subscribers only field
Freemium Only 2015 Turbine Bold Tern arrived on site and is believed to have ... Subscribers only field Subscribers only field
Freemium Only 2015 Turbine DP2 THOR was used to carry out heavy maintenance w... Subscribers only field Subscribers only field
Freemium Only 2015 Turbine Just one month following its official inauguration... Subscribers only field Subscribers only field
Freemium Only 2015 Fully Commissioned Nordsee Ost was officially inaugurated on this day... Subscribers only field Subscribers only field
Freemium Only 2014 Generating Power HelWin1 grid connection was completed and Nordsee ... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation The 48th and final turbine was installed over the ... Subscribers only field Subscribers only field
Freemium Only 2014 Generating Power The first of the projects 48 wind turbines commenc... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 24 of 48 turbines were completed, also all of the ... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation A total of 19 turbines have been installed in just... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 15 turbines were installed.... Subscribers only field Subscribers only field
Freemium Only 2014 Offshore Substation The 1,800 ton offshore substation topside was inst... Subscribers only field Subscribers only field
Freemium Only 2014 Offshore Substation The offshore substation was ready for departure fr... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation The first Senvion turbine was installed during thi... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation The 63km of array cabling was installed. The cabli... Subscribers only field Subscribers only field
Freemium Only 2014 Grid Connection Other The grid connection was put back to mid-2014 due t... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation First four 240-tonnes tubular steel towers, with a... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation All of the foundations were installed (48 turbines... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation FoundOcean completed the grouting of the 48 turbin... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation A number of ammunitions will need to be destroyed ... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation Initial scheduling stated foundation installation ... Subscribers only field Subscribers only field
Freemium Only 2014 Offshore Substation The 400 tonne top was placed on the bottom of the ... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation Victoria Mathias is currently installing the jacke... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Due to a period of bad weather, foundation install... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Foundation installation was ongoing. Installation ... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation In total 25 (of 52) array cables were installed wi... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Approximately 30 foundations are now in place.... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation RWE Innogy started laying the first inter array ca... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 24 foundations have been installed to date, 24 rem... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Substation foundation was installed in Summer 2013... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 18 of the 48 foundations were installed.... Subscribers only field Subscribers only field
Freemium Only 2013 Export Cable Installation The HVAC export cable works started and completed ... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Six of the 48 foundations have been installed.... Subscribers only field Subscribers only field
Freemium Only 2012 Other Approval Offshore construction start deadline issued by BSH... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Four foundations in place.... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Installation of the first jacket foundation commen... Subscribers only field Subscribers only field
Freemium Only 2012 Site Investigation Geophysical analysis using MS Sölöven and MS Reykj... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Victoria Mathias was unable to load foundations du... Subscribers only field Subscribers only field
Freemium Only 2012 Offshore Construction Starts Construction started in July 2012.... Subscribers only field Subscribers only field
Freemium Only 2011 Financial Close Financial Investment Decision took place.... Subscribers only field Subscribers only field
Freemium Only 2011 Met Mast/LiDAR The met mast was installed.... Subscribers only field Subscribers only field
Freemium Only 2004 Consent Authorised Consent authorisation was given by the Federal Mar... Subscribers only field Subscribers only field
Freemium Only 2000 Consent Application Submitted Date of application.... Subscribers only field Subscribers only field