Events on Trianel Windpark Borkum I

As an Offshore Wind Farm Subscriber, you can follow this project to add it to your dashboard.

Follow this project
Germany 200MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Trianel Windpark Borkum I

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2020 Foundation Trianel Wiindpark Borkum has issued a tender for s... Subscribers only field Subscribers only field
Freemium Only 2020 Turbine Service Agreement Expires The five-year OEM service agreement will expire ar... Subscribers only field Subscribers only field
Freemium Only 2020 Tender Process Trianel Windkraftwerk Borkum GmbH issued a tender ... Subscribers only field Subscribers only field
Freemium Only 2020 Health and Safety CTV Njord Forseti reported a collision with a wind... Subscribers only field Subscribers only field
Freemium Only 2019 Tender Process Trianel Windkraftwerk Borkum GmbH and Co. KG has i... Subscribers only field Subscribers only field
Freemium Only 2019 Tender Process Trianel wind power plant Borkum GmbH & Co. KG has ... Subscribers only field Subscribers only field
Freemium Only 2019 Trianel issued a tender on 1st October 2019 for co... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine SkySpecs carried out inspections of the wind turbi... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable A cable fault occurred in the three-phase connecti... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable A cable fault occurred in the three-phase connecti... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Jack up vessel Neptune arrived on site to support ... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Heavy maintenance work was carried out on turbine ... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Brave Tern was on site during March to carry out h... Subscribers only field Subscribers only field
Freemium Only 2016 Performance Monitoring After 6 months in operation the wind farm had a 90... Subscribers only field Subscribers only field
Freemium Only 2016 Performance Monitoring In January the wind farm produced 95.12GWh, the hi... Subscribers only field Subscribers only field
Freemium Only 2015 Fully Commissioned The wind farm was inaugurated. Johannes Remmel, Mi... Subscribers only field Subscribers only field
Freemium Only 2015 Grid Connection Available DolWin1 was fully commissioned, meaning Trianel ha... Subscribers only field Subscribers only field
Freemium Only 2015 Array Cable VBMS completed the repair of an inter-array cable ... Subscribers only field Subscribers only field
Freemium Only 2015 Generating Power Following the commissioning of the last turbine, a... Subscribers only field Subscribers only field
Freemium Only 2015 Array Cable VBMS completed the repair of an inter-array cable ... Subscribers only field Subscribers only field
Freemium Only 2015 Final Testing A total of 20 of the 40 turbines were commissioned... Subscribers only field Subscribers only field
Freemium Only 2015 Generating Power First power took place (was summer 2014), due to d... Subscribers only field Subscribers only field
Freemium Only 2014 Grid Connection Available Permanent power connection was successfully establ... Subscribers only field Subscribers only field
Freemium Only 2014 Final Testing Trial operations and testing of transformer substa... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation Array cable installation was completed with all 43... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation The turbine installation was completed. It took 11... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation The 39th turbine was installed, with the final tur... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 28 of the 40 turbines were installed.... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 25 of the 40 turbines have been installed.... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 75% of the array cabling has been installed.... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 20 of the 40 Areva turbines have now been installe... Subscribers only field Subscribers only field
Freemium Only 2014 Tender Process Tender for the supply of accommodation and crew tr... Subscribers only field Subscribers only field
Freemium Only 2014 Due to TenneT's delay in supplying the grid connec... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 13 turbines have been fully installed.... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation Array cable installation was originally scheduled ... Subscribers only field Subscribers only field
Freemium Only 2013 Offshore Substation The offshore substation and associated jacket foun... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Over a two-day period, the first turbine was insta... Subscribers only field Subscribers only field
Freemium Only 2013 Tender Process The tender is for diving services including vessel... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation Technip Offshore Wind started offshore operations ... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Foundation installation complete: the last of the ... Subscribers only field Subscribers only field
Freemium Only 2013 Offshore Substation The offshore substation installation was completed... Subscribers only field Subscribers only field
Freemium Only 2013 Production and Fabrication All the components for the turbines have been pre-... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Currently 21 of 40 foundations are installed.... Subscribers only field Subscribers only field
Freemium Only 2013 Financing Agreement A further EIB signature date of €5,487,461 on 6th... Subscribers only field Subscribers only field
Freemium Only 2013 Other The 40 wind turbines have been shipped to Eemshave... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation The transformer foundation was loaded onto the Vik... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation 20 tripod foundations installed, a further 3 expec... Subscribers only field Subscribers only field
Freemium Only 2012 Other Trianel filed a suit against TenneT due to delays ... Subscribers only field Subscribers only field
Freemium Only 2012 Site Investigation Geophysical Surveying with multibeam, side scan so... Subscribers only field Subscribers only field
Freemium Only 2012 Grid Connection Agreed Unconditional grid offer in place with TenneT.... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Update: 10 tripods of 600-800 tonnes (direct comms... Subscribers only field Subscribers only field
Freemium Only 2012 Offshore Substation The substation was installed in July 2012.... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Foundation installation started in June 2012.... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Update: Prepiling by Geosea's Goliath is now compl... Subscribers only field Subscribers only field
Freemium Only 2012 Production and Fabrication 20 turbines have been delivered by Areva to the po... Subscribers only field Subscribers only field
Freemium Only 2012 Other Update: 26 of 40 pre-piles installed.... Subscribers only field Subscribers only field
Freemium Only 2011 Foundation Installation Prepiling of foundations started.... Subscribers only field Subscribers only field
Freemium Only 2010 Financing Agreement The Environmental Investment Bank (EIB) to provide... Subscribers only field Subscribers only field
Freemium Only 2010 Financial Close Financial Close. The European Investment Bank and ... Subscribers only field Subscribers only field
Freemium Only 2008 Consent Authorised Consent authorisation was given by the Federal Mar... Subscribers only field Subscribers only field
Freemium Only 2006 Consent Application Submitted Date of application to authorities.... Subscribers only field Subscribers only field