Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.
Events on Northwind Database in Excel
DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The fifteen-year OEM service agreement will expire.
Source: LogIn
correct
30-Jun-2014 Event Type: Operation - Fully Commissioned
Fully Commissioned The turbine installation was completed in May and a report stated that the project was completed at the end of June.
Source: LogIn
correct
02-Jun-2014 Event Type: Installation - Final Testing
Final Testing The site is currently being visited by 7 crew and service vessels as commissioning continues.
Source: LogIn
correct
29-Apr-2014 Event Type: Installation - Turbine Installation
Turbine Installation On this day GeoSea's Neptune left the site after completing installation of the final Vestas V112-3.0MW turbine.
Source: LogIn
correct
Mar-2014 Event Type: Installation - Turbine Installation
Turbine Installation GeoSea's Neptune arrived on site to aid turbine installation. On the 4th March, MPI Resolution left the site and demobilised from the project.
Source: LogIn
correct
14-Jan-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation Array cable installation completed.
Source: LogIn
correct
29-Dec-2013 Event Type: Installation - Turbine Installation
Turbine Installation Installation vessel MPI Resolution is continuing to install turbines at the project. Despite initial reports suggesting that up to four vessels would be used for turbine installation, there is currently only one on site.
Source: LogIn
correct
25-Oct-2013 Event Type: Installation - Turbine Installation
Turbine Installation 30 turbines had been installed.
Source: LogIn
correct
25-Oct-2013 Event Type: Installation - Array Cable Installation
Array Cable Installation 44 array cables had been installed.
Source: LogIn
correct
17-Sep-2013 Event Type: Installation - Turbine Installation
Turbine Installation 18 turbines had been installed.
Source: LogIn
correct
09-Sep-2013 Event Type: Installation - Foundation Installation
Foundation Installation Neptune left the site, marking the end of monopile and transition piece installation.
Source: LogIn
correct
22-Aug-2013 Event Type: Installation - Export Cable Installation
Export Cable Installation Notice to Mariners states that the export cable has been laid but is currently exposed.
Source: LogIn
correct
22-Jul-2013 Event Type: Installation - Turbine Installation
Turbine Installation MPI Resolution arrived at the project site marking the start of turbine installation activities.
Source: LogIn
correct
16-Jul-2013 Event Type: Installation - Array Cable Installation
Array Cable Installation Installation of the 72 array cables began: multi-purpose vessel Olympic Taurus will be responsible for the cable lay and burial, utilising the Perry Slingsby Triton XLS42 ROV.
Source: LogIn
correct
Jul-2013 Event Type: Installation - Export Cable Installation
Export Cable Installation The 245kV export cable installation began mid-2013 using the MPV Willem De Vlamingh.
Source: LogIn
correct
Jul-2013 Event Type: Installation - Offshore Substation
Offshore Substation On 1st July the Northwind offshore substation was installed on its monopile foundation.
Source: LogIn
correct
30-Jun-2013 Event Type: Installation - Offshore Substation
Offshore Substation The substation will be transported to Aalborg on 22/06/2013 at the earliest. From here the substation will be transported to the site for installation.
Source: LogIn
correct
29-May-2013 Event Type: Installation - Foundation Installation
Foundation Installation Estimated that 13 monopiles and transition pieces had been installed by the Neptune.
Source: LogIn
correct
07-Apr-2013 Event Type: Installation - Offshore Construction Starts
Offshore Construction Starts The offshore construction works started.
Source: LogIn
correct
07-Apr-2013 Event Type: Installation - Foundation Installation
Foundation Installation Installation of the monopile foundations began with the arrival of Neptune on site.
Source: LogIn
correct
Feb-2013 Event Type: Installation - Other
Other Offshore transformer station delivered to Bladt and being outfitted with electrical equipment and mechanical systems in Aalborg. Expected finish was June 2013.
Source: LogIn
correct
28-Jun-2012 Event Type: Planning - Financing Agreement
Financing Agreement As part of the financial agreement the EIB will finance €333m.
Source: LogIn
correct
28-Jun-2012 Event Type: Planning - Financial Close
Financial Close Financial Close occurred. Lenders for the project are ASN Bank, Belfius, BNP Paribas Fortis, the European Investment Bank, ING, KfW IPEX, the Norwegian Ministry of Trade and Industry, Rabobank, Eksport Kredit Fonden, Office National Du Ducroire and Garanti Instituttet for eksportkreditt.
Source: LogIn
correct
20-Mar-2012 Event Type: Planning - Financing Agreement
Financing Agreement European Investment Bank (EIB) to provided €350m of debt finance.
Source: LogIn
correct
06-Jun-2011 Event Type: Planning - Financing Agreement
Financing Agreement The shareholders approved an increase of €15m to the project’s capital budget.
Source: LogIn
correct
11-Nov-2009 Event Type: Planning - Consent Authorised
Consent Authorised Permits for construction and operation granted.
Source: LogIn
correct
15-May-2006 Event Type: Planning - Consent Application Submitted
Consent Application Submitted Consent Application Submitted.
Source: LogIn
correct
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/events.aspx?windfarmID=be02.