14 Sep 2021: The arbitration tribunal judged that CIP has to pay Taiwan Generations Corporation (TGC) NT$150 million milestone fee. CIP today clarified that the two parties have different interpretations of the payment terms at the milestones of the contract. They are not breaking the contract without reason, but they still respect the arbitral tribunal's right to interpret the contract, and the payment has been completed. CIP emphasized that the agreement on the milestone payment of the Fufang Wind Farm service contract is based on whether the Fufang Wind Farm can continue to develop smoothly when it reaches each milestone.
Location:
Taiwan
Status:
Cancelled
Capacity:
600 MW
4C Offshore | Location Map: Lat(23.920) Lon(120.080)

Subscribers can track wind farms on their dashboard.

General Information
Name
Fufang
Other Names
彰化福芳離岸風力發電計畫 Offshore Wind Power Project of Changhua Fofang Changhua 6-2 - Development Zone ZoP 28
Country
Taiwan
Development Status
Cancelled
Category or Round
Unlock with a freemium account
Region
Comments
Website

Developers/Owners/Operators
Type
Organisation

Offshore Construction Starts
Submitted For Consent
Consent Authorised
Financial Close
First Power
Full Commissioning

Revenue Mechanism
Revenue Details
Revenue
/MWh (EUR /MWh)

Login to Improve Information Access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads.

Sign up now!
Power & Turbines
Windfarm Capacity
600 MW
Turbine Model
Unlock with a freemium account
Other Turbine(s) Used
Min. Turbine Capacity (MW)
Max. Turbine Capacity (MW)
Min. Number of Turbines
Unlock with a freemium account
Max. Number of Turbines
Total Turbine Height
Hub Height
Rotor Diameter
Foundation Type
Unlock with a freemium account
Foundations on Wind Farm
Foundation Comments

Location & Environment
Sea Name
Taiwan Strait
Latitude
23.919816°
Longitude
Area
Unlock with a freemium account
Depth Range (Chart Datum)
Depth Range (Stated by Developer)
Distance from Shore (Developer)
Unlock with a freemium account
Distance from Shore (Computed)

Ports
Installation Base
Unlock with a freemium account
Ops and Maintenance
Unlock with a freemium account

Grid
Number of Offshore Platform(s)
1
Shared Platform Type
Grid Connection Point
Cable Landing Point

Export Cables (AC & DC)
Number of Export Cables (AC)
Unlock with a freemium account
Average Length per Cable (AC)
Additional Requirements (AC)
Nominal Voltage (AC)
Number of Export Cables (DC)
Average Length per Cable (DC)
Unlock with a freemium account
Additional Requirements (DC)
Nominal Voltage (DC)

Nominal Voltage
Comments

Onshore Cables
Number of Onshore Cables
Average Length per Cable
Comments
Expected Life