United Kingdom 588MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Beatrice

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2020 Consultation The UK government is proposing an exemption order ... Subscribers only field Subscribers only field
Freemium Only 2019 Tender Process Marine Scotland published the draft Sectoral Marin... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Fugro Frontier is surveying 10 turbines, 12 inter-... Subscribers only field Subscribers only field
Freemium Only 2019 Offshore Substation Seajacks Scylla arrived on Beatrice to provide acc... Subscribers only field Subscribers only field
Freemium Only 2019 Offshore Substation A power outage was reported at OTM 1. Works are ex... Subscribers only field Subscribers only field
Freemium Only 2019 Generating Power An opening ceremony was held at SSE's office in Wi... Subscribers only field Subscribers only field
Freemium Only 2019 Financing Agreement Beatrice Offshore Windfarm Ltd (BOWL), achieved a ... Subscribers only field Subscribers only field
Freemium Only 2019 Fully Commissioned Update: According to the 3rd June Notice of Operat... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Update: Pacific Orca installed the final turbine o... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement Global Port Services completed pre-assembly activi... Subscribers only field Subscribers only field
Freemium Only 2019 Foundation Seaway 7 has resumed its maintenance programme on ... Subscribers only field Subscribers only field
Freemium Only 2019 Generating Power Phase 1 CfD payments started on 6 November 2018 an... Subscribers only field Subscribers only field
Freemium Only 2019 Tender Process OFGEM has shortlisted bidders for three offshore w... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement Pre-assembly of the final tower was completed by W... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation 69 of the 84 SWT-7.0-154 turbines have been insta... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Construction update: Turbine installation is compl... Subscribers only field Subscribers only field
Freemium Only 2019 Tender Process Ofgem to complete the EPQ bidding and evaluation p... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Turbine installation completed at 58 locations and... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Two thirds of the turbines has been installed.... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation 42 out of 84 Siemens Gamesa 7MW wind turbines have... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation Turbine installation has been completed at 39 loca... Subscribers only field Subscribers only field
Freemium Only 2018 Tender Process OFGEM published a notice under the electricity (co... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation Turbine installation has been completed at 33 loca... Subscribers only field Subscribers only field
Freemium Only 2018 Generating Power On 6th November, BOWL submitted a ‘Start Date Noti... Subscribers only field Subscribers only field
Freemium Only 2018 Tender Process Ofgem intends to commence tender exercises for Off... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation 26 WTG installed, 21 WTG commissioned.... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation Jan de Nul completed Campaign 1 (of 3) rock berm l... Subscribers only field Subscribers only field
Freemium Only 2018 Tender Process Offshore Transmission Owner (OFTO) Tender Round Si... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation 24 WTG installed and 20 turbines commissioned... Subscribers only field Subscribers only field
Freemium Only 2018 Grid Connection Available National Grid will provide the next 259MW of grid ... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation Jan De Nul will conduct the array cable rock place... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation 20 turbines have been installed and 16 have been c... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation Seaway Heavy Lifting completed the third array cab... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation Ten turbines have been installed so far.... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation Four turbines have been installed so far.... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation Siem Aimery returned to Hartlepool to commence loa... Subscribers only field Subscribers only field
Freemium Only 2018 Generating Power Beatrice Offshore Windfarm Limited exported power ... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Installation The first turbine was installed.... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement Pacific Orca heading to the wind farm site to comm... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation The final jacket foundation was installed.... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation Seaway Heavy Lifting complete installation of 75th... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation The rock emplacement campaign for the installation... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation 66 (of 86) jacket substructures installed.... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation EC1 and OTM1 was energised on the 1st June. On the... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation The CLV Siem Aimery has completed the 2nd Inter Ar... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation 64 (of 86) jacket substructures installed.... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation 56 (of 86) jacket substructures installed.... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation Nexans Norway AS, has completed all export cable i... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation Installation of the second OTM is ongoing. The Jac... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation Foundation installation completed at 51 Locations... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation Nexans Skagerrak has completed the pull-in of the ... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation The CLV Siem Aimery left site and will return at a... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation The second Offshore Transformer Module (OTM) jacke... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation The fourth campaign of the installation of the two... Subscribers only field Subscribers only field
Freemium Only 2018 Onshore Cable Installation The first of the two 400 kV onshore cable links an... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement Nexans factory in Norway has completed the manufac... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation Foundation installation completed at 45 Locations.... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation Nexans Skagerrak and Island Crown have completed t... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation The CLV Siem Aimery has so far installed 7 array c... Subscribers only field Subscribers only field
Freemium Only 2018 Grid Connection Available National Grid will provide the first 294MW of grid... Subscribers only field Subscribers only field
Freemium Only 2018 Cable installation Nexans Skagerrak and Island Crown have completed t... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation Siemens Transmission and Distribution Ltd. are car... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation The CLV Siem Aimery will install up to 34 Inter Ar... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation CLV Nexans Skagerrak completed the pullin of the f... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation Nexans Skagerrak will commence pull in of the firs... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation Foundation installation complete at 43 locations.... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation The first Siemens Offshore Transformer module was ... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement The first OTM has left the port of Rosyth and is o... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation The first of the jackets for the two Offshore Tran... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation The first section of the second export cable arriv... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation Foundation installation completed at 37 locations.... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation Foundation installation completed at 34 Locations.... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation The rock emplacement campaign for the installation... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Foundation installation completed at 32 Locations.... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Foundation installation completed at 28 Locations... Subscribers only field Subscribers only field
Freemium Only 2017 Array Cable Installation CLV Siem Aimery installed 16 cables during campai... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation All work on the first export cable was completed a... Subscribers only field Subscribers only field
Freemium Only 2017 Array Cable Installation Siem Aimery has installed 13 array cables (8 insta... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Piling work was completed at all turbine locations... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Foundation installation by Oleg Strashnov resumed ... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Oleg Strashnov returned to site on 16th November ... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation The export cable has now been jointed and surface ... Subscribers only field Subscribers only field
Freemium Only 2017 Burntisland Fabrications Limited (BiFab) announced... Subscribers only field Subscribers only field
Freemium Only 2017 Array Cable Installation The first campaign of the installation of the arra... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Pre-piling nears completion; 84 of the 86 sets hav... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation The second campaign of export cable installation i... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Pre-piling work by Seaway Heavy Lifting for the fo... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation The Nexans Skagerrak is at the Port of Halden in N... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation Nexans began installation of the export cable syst... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Jacket installation halts at 24 installed, until p... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation 72 pile clusters complete and 18 jacket foundation... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement Bladt Industries has delivered the first four of t... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation More than three quarters of the foundation piles h... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Six of the 86 foundations have been installed by O... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement JDR finished manufacturing the array cables, now r... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Successful installation of the first of the 86 jac... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement Burntisland Fabrications will deliver the first 10... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation Half of the turbine foundation piles have now been... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement More than half of the submarine composite cables f... Subscribers only field Subscribers only field
Freemium Only 2017 Construction - Seabed Preparation Ecosse Subsea Systems completed a 14-day seabed cl... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The Stanislav Yudin has installed 29 sets of turbi... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement Bladt completed the first jacket foundation by sta... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The Stanislav Yudin has installed 25 sets of turbi... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement The first transformer for the onshore substation l... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The Stanislav Yudin has installed 21 sets of turbi... Subscribers only field Subscribers only field
Freemium Only 2017 Construction - Seabed Preparation From June to August the cable runs will be excavat... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The Stanislav Yudin has installed 17 sets of turbi... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The Stanislav Yudin has installed nine sets of tur... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement Bladt completed the first lifting operation at its... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The second set of piles, manufactured by BiFab in ... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The first set of piles was installed during the ev... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The vessel Stanislav Yudin started to install the ... Subscribers only field Subscribers only field
Freemium Only 2017 Construction - Seabed Preparation For a duration of 7 days the Siem Ruby will perfor... Subscribers only field Subscribers only field
Freemium Only 2017 Construction - Seabed Preparation SSE and the Navy disposed of a 1,000lb explosive d... Subscribers only field Subscribers only field
Freemium Only 2017 Other Work on the Operations and Maintenance (O&M) site ... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Smulders completed the first section for the 28 ja... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Burntisland Fabrications has begun fabrication of ... Subscribers only field Subscribers only field
Freemium Only 2016 Onshore Construction Starts An important milestone was reached as onshore cons... Subscribers only field Subscribers only field
Freemium Only 2016 Site Investigation The vessel Fugro Helmet, Fugro Frontier and Meridi... Subscribers only field Subscribers only field
Freemium Only 2016 Other Approval Low Carbon Contracts Company (LCCC) announced that... Subscribers only field Subscribers only field
Freemium Only 2016 Site Investigation An unexploded ordnance survey along the export cab... Subscribers only field Subscribers only field
Freemium Only 2016 Financing Agreement As part of reaching financial close, the European ... Subscribers only field Subscribers only field
Freemium Only 2016 Financial Close The £2.6 billion Beatrice Offshore Windfarm Ltd (B... Subscribers only field Subscribers only field
Freemium Only 2016 Ownership Change Repsol sold their 25% stake in Beatrice to SDIC Po... Subscribers only field Subscribers only field
Freemium Only 2015 Other Approval Beatrice Offshore Windfarm Ltd has been granted pe... Subscribers only field Subscribers only field
Freemium Only 2015 Draft decommissioning prepared for informal consul... Subscribers only field Subscribers only field
Freemium Only 2015 Site Investigation The vessels FV ANTARIES and FV PLEIADES carried ou... Subscribers only field Subscribers only field
Freemium Only 2015 Geotechnical Site Investigation MMT Ltd carried out geophysical and geotechnical s... Subscribers only field Subscribers only field
Freemium Only 2015 Financing Agreement Proposed finance of £525 million from the European... Subscribers only field Subscribers only field
Freemium Only 2015 Site Investigation APEM Limited carried out a marine environmental in... Subscribers only field Subscribers only field
Freemium Only 2015 Geotechnical Site Investigation Fugro are carrying out another Geotechnical survey... Subscribers only field Subscribers only field
Freemium Only 2015 Geotechnical Site Investigation Fugro were undertaking geotechnical site investiga... Subscribers only field Subscribers only field
Freemium Only 2015 Site Investigation In early January BOWL undertook an UXO survey, ahe... Subscribers only field Subscribers only field
Freemium Only 2015 Following the conclusions of the report in March 2... Subscribers only field Subscribers only field
Freemium Only 2014 Site Investigation Fugro's vessel Fugro Pioneer undertook Geophysical... Subscribers only field Subscribers only field
Freemium Only 2014 Geotechnical Site Investigation Fugro GeoConsulting Ltd's MV Gargano performed sur... Subscribers only field Subscribers only field
Freemium Only 2014 Site Investigation Brown and May commenced larval sampling at 25 loca... Subscribers only field Subscribers only field
Freemium Only 2014 Financing Agreement One of eight renewable energy projects to sign con... Subscribers only field Subscribers only field
Freemium Only 2014 Subsidy/PPA Conditionally Secured Offered an early stage Contracts for Difference (C... Subscribers only field Subscribers only field
Freemium Only 2014 From an Interim Management Statement released 22/0... Subscribers only field Subscribers only field
Freemium Only 2014 Other Application Submitted A final investment contract application was submit... Subscribers only field Subscribers only field
Freemium Only 2014 Consent Authorised Having carried out assessments of the potential en... Subscribers only field Subscribers only field
Freemium Only 2013 Other Approval DECC sent draft investment contracts to applicants... Subscribers only field Subscribers only field
Freemium Only 2013 Other Approval The Government announced the qualifying projects f... Subscribers only field Subscribers only field
Freemium Only 2013 Other Approval The Highland Council is due to meet and raise no o... Subscribers only field Subscribers only field
Freemium Only 2013 Other Approval The Moray Council has granted Planning Permission ... Subscribers only field Subscribers only field
Freemium Only 2012 Other Application Submitted An application was made to Moray Council for the o... Subscribers only field Subscribers only field
Freemium Only 2012 Other Approval An Electrical Generation Licence was granted to th... Subscribers only field Subscribers only field
Freemium Only 2012 Other Application Submitted The consent application was formally accepted.... Subscribers only field Subscribers only field
Freemium Only 2012 Consent Application Submitted Application for Beatrice Offshore Wind Farm and Be... Subscribers only field Subscribers only field
Freemium Only 2011 Other Approval The Crown Estate awarded agreements for lease for ... Subscribers only field Subscribers only field
Freemium Only 2011 Site Investigation In the report Blue Seas-Green Energy it was found ... Subscribers only field Subscribers only field