As an Offshore Wind Farm Subscriber, you can follow this project to add it to your dashboard.

Follow this project
United Kingdom 576MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Gwynt y Môr

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2020 Environmental and Seabed Monitoring Modus Subsea Services will undertake seabed invest... Subscribers only field Subscribers only field
Freemium Only 2020 Cable In Lord Justice Philips’ ruling on 8 April 2020, t... Subscribers only field Subscribers only field
Freemium Only 2019 Ownership Change Macquarie Infrastructure and Real Assets (MIRA) ha... Subscribers only field Subscribers only field
Freemium Only 2019 Health and Safety A casualty involving a fishing boat whose motor ha... Subscribers only field Subscribers only field
Freemium Only 2019 Onshore Substation A failure event to the onshore substation resulted... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine J/U WIND SERVER arrived on site to carry out maint... Subscribers only field Subscribers only field
Freemium Only 2019 Environmental and Seabed Monitoring Bibby HydroMap Limited will be carrying out a bath... Subscribers only field Subscribers only field
Freemium Only 2019 EDS HV re-visited the windfarm to complete further... Subscribers only field Subscribers only field
Freemium Only 2018 Other Jack-up vessel WIND undertaking maintenance work a... Subscribers only field Subscribers only field
Freemium Only 2018 Environmental and Seabed Monitoring Bathymetric and sidescan survey operations took pl... Subscribers only field Subscribers only field
Freemium Only 2018 Environmental and Seabed Monitoring Bibby HydroMap Limited commenced hydrographic surv... Subscribers only field Subscribers only field
Freemium Only 2018 Environmental and Seabed Monitoring Geophysical survey operations carried out by Fugro... Subscribers only field Subscribers only field
Freemium Only 2018 EDS HV Group completed trials of its solution that... Subscribers only field Subscribers only field
Freemium Only 2017 innogy placed the first German corporate Green Bon... Subscribers only field Subscribers only field
Freemium Only 2017 Other The vessel MV Meridian is due to carry out a geoph... Subscribers only field Subscribers only field
Freemium Only 2017 Array Cable A recent seabed survey has identified areas where ... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine The vessel J/U WIND SERVER arrived on site to carr... Subscribers only field Subscribers only field
Freemium Only 2016 Site Investigation The vessel Aquadynamic began a survey of the sea b... Subscribers only field Subscribers only field
Freemium Only 2016 Environmental and Seabed Monitoring The vessel Fugro Helmert will carry out geophysica... Subscribers only field Subscribers only field
Freemium Only 2016 Performance Monitoring From March 2015 to March 2016 Gwynt Y Mor OFTO onl... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable The Stemat Spirit arrived on-site to commence repa... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable A further electrical fault occurred early on the 2... Subscribers only field Subscribers only field
Freemium Only 2015 Environmental and Seabed Monitoring Until the 15th September, the Greatship Manisha wi... Subscribers only field Subscribers only field
Freemium Only 2015 Other A survey involving diving operations was carried o... Subscribers only field Subscribers only field
Freemium Only 2015 Other An offshore GIS failure occurred at Gwynt y Môr in... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable Following recent cable maintenance works, it has c... Subscribers only field Subscribers only field
Freemium Only 2015 Fully Commissioned Official inauguration took place. The wind farm wa... Subscribers only field Subscribers only field
Freemium Only 2015 Array Cable Installation EDS has now completed all high voltage and fibre o... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable A fault occurred at the SSEC1 export cable. The fa... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable A fault occurred at the SSEC1 export cable. The fa... Subscribers only field Subscribers only field
Freemium Only 2015 RWE Innogy and the Carbon Trust's Offshore Wind Ac... Subscribers only field Subscribers only field
Freemium Only 2015 Grid Connection Available An addition of 9MW capacity was provided to the on... Subscribers only field Subscribers only field
Freemium Only 2015 Ofgem appointed Gwynt y Môr OFTO (Balfour Beatty E... Subscribers only field Subscribers only field
Freemium Only 2015 Other Rock dumping vessel Seahorse is still undertaking ... Subscribers only field Subscribers only field
Freemium Only 2014 Met Mast/LiDAR The FLIDAR buoy was removed by the crane barge LAr... Subscribers only field Subscribers only field
Freemium Only 2014 Other Scour protection work commenced in late November. ... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation The final array cable has been installed at the wi... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation No further array cable update has been made availa... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation Array cable installation is continuing at the site... Subscribers only field Subscribers only field
Freemium Only 2014 Other Scour is due to commence on 21/09/2014. On the 22/... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation No further progress has been made regarding the ar... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 142 array cables have now been installed with a fu... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 137 array cables have now been installed with a fu... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation Fugro successfully complete trenching and burial w... Subscribers only field Subscribers only field
Freemium Only 2014 Generating Power The 81st (of 160) turbine was connected to the gri... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 128 array cables are now installed, with a further... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 127 array cables are now installed, with a further... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation No further progress has been made on the array cab... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation No more array cables have been installed since the... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation According to the public construction updates, ther... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation In the week starting 30th June there were no new c... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation There are currently 119 array cables installed wit... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation On 28 June 2014, the last turbine completed instal... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation There are currently 118 array cables installed wit... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 113 array cables are currently installed, with a f... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation There are currently 157 turbines installed with 3 ... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation There are currently 109 array cables installed wit... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 154 wind turbine generators have now been installe... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 92 array cables have now been installed, with a fu... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 151 wind turbine generators have now been installe... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 86 array cables are now installed, with a further ... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 150 wind turbine generators are now installed, wit... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 80 array cables are now installed, with a further ... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 146 wind turbine generators are now installed, wit... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 77 array cables are installed, with a further 84 r... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 144 wind turbine generators are installed, with a ... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 142 wind turbine generators have been installed, w... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 54 array cables have been installed, with a furthe... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation All transition pieces were installed. Thus the fou... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 53 array cables have now been installed, with 108 ... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 136 wind turbine generators have now been installe... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation 159 transition pieces have now been installed, wit... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 50 array cables have now been installed with a fu... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 129 wind turbine generators have now been installe... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 47 array cables have now been installed with a fur... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation 156 transition pieces have now been installed, wit... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 124 wind turbine generators have now been installe... Subscribers only field Subscribers only field
Freemium Only 2014 Other The third and last UXO was disposed of therefore e... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 42 array cables have now been installed with a fur... Subscribers only field Subscribers only field
Freemium Only 2014 Other The first of the three UXO was detonated with the ... Subscribers only field Subscribers only field
Freemium Only 2014 Other A 1km exclusion zone was put in place around three... Subscribers only field Subscribers only field
Freemium Only 2014 Other No further progress has been made since the previo... Subscribers only field Subscribers only field
Freemium Only 2014 A Marine Licence to remove three pieces of unexplo... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation 155 transition pieces have now been installed, wit... Subscribers only field Subscribers only field
Freemium Only 2014 World War II munitions have been found at the site... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 123 wind turbine generators have now been installe... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 39 array cables have now been installed with a fur... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation No further progress has been made on the transitio... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation 153 transition pieces are now installed, with a fu... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 119 wind turbine generators are now installed, wit... Subscribers only field Subscribers only field
Freemium Only 2014 Other It was reported that unexploded munitions had been... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation 152 transition pieces are currently installed, wit... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 38 array cables are currently installed with 123 r... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 115 wind turbine generators are currently installe... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation 150 transition pieces have now been installed, wit... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 37 array cables have now been installed with 124 r... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 113 wind turbine generators have now been installe... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation The 112th turbine was installed. A2Sea released a ... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation 149 transition pieces have now been installed, wit... Subscribers only field Subscribers only field
Freemium Only 2014 Foundation Installation 148 transition pieces are now installed, with 12 r... Subscribers only field Subscribers only field
Freemium Only 2014 Array Cable Installation 35 array cables are now installed, with 126 remain... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Installation 107 wind turbine generators are installed, with 53... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 146 transition pieces were installed to date with ... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 107 turbines were installed to date with 53 remain... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 145 transition pieces were installed to date with ... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 34 array cables were installed to date with 127 re... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 104 turbines were installed to date with 56 remain... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation The 100th turbine was installed at 01:30 hours wit... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 30 array cables are currently installed, with a fu... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 98 wind turbine generators are currently installed... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 144 transition pieces are currently installed, wit... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 92 wind turbine generators are currently installed... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 140 transition pieces are installed, with a furthe... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 84 wind turbine generators are installed, with a f... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 139 transition pieces have now been installed, wit... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 28 array cables have now been installed, with a fu... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 82 wind turbine generators have now been installed... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 139 transition pieces have now been installed, wit... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 81 wind turbine generators have been installed, wi... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 76 turbines were installed, with 84 remaining. The... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 137 transition pieces were installed, a further 25... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 27 array cables were installed, a further 134 rema... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 74 turbines were installed, a further 86 remain.... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 136 transition pieces were installed, a further 24... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 24 array cables have been installed, a further 137... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 71 Wind Turbine Generators (WTGs) have been instal... Subscribers only field Subscribers only field
Freemium Only 2013 Grid Connection Available 420MW of grid connection was made available and a ... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 132 transition pieces are now installed, a further... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 67 Wind Turbine Generators (WTGs) are now installe... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 127 transition pieces have been installed, a furth... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 21 array cables have been installed, a further 140... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 62 Wind Turbine Generators (WTGs) have been instal... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 124 transition pieces have been installed, with 36... Subscribers only field Subscribers only field
Freemium Only 2013 Generating Power The project exported power for the first time.... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 118 transition pieces have been installed, with 42... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 18 array cables have been installed with 143 now r... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 57 wind turbine generators have been installed, wi... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 112 transition pieces have been installed with 48 ... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 55 turbines have been installed with 105 remaining... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation All 160 monopiles are now installed. 108 transitio... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 50 turbines have been installed with 110 remaining... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 17 array cables have been installed with 144 remai... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 152 monopiles have been installed with 8 remaining... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 44 turbines have been installed, 116 are remaining... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 14 array cables have been installed 147 remaining.... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 146 monopiles were installed with 14 remaining and... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 12 of 160 array cables were installed with the exp... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 41 turbines were installed with 119 remaining.... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 138 monopiles are installed with 22 remaining and ... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation 11 of 160 array cables were installed with the exp... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 34 turbines were installed with 126 remaining.... Subscribers only field Subscribers only field
Freemium Only 2013 Met Mast/LiDAR A floating LiDAR was positioned next to the tradit... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Construction Update:
Monopiles: 122 installed, 38... Subscribers only field
Subscribers only field
Freemium Only 2013 Export Cable Installation The fourth and final export cable was installed an... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Construction Update:
Monopiles: 101 installed, 59... Subscribers only field
Subscribers only field
Freemium Only 2013 Export Cable Installation The third export cable installation was installed ... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Construction Update:
Monopiles: 87 installed, 73 ... Subscribers only field
Subscribers only field
Freemium Only 2013 Turbine Installation To date three turbines have been installed with 15... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation 81 monopiles have been installed with 79 remaining... Subscribers only field Subscribers only field
Freemium Only 2013 Export Cable Installation The 2nd eastern export cable was installed.... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation The first Siemens 3.6MW turbine was installed at t... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation The installation of 80 foundations and 32 transiti... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Construction update:
Monopiles: 80 installed, 80 ... Subscribers only field
Subscribers only field
Freemium Only 2013 Export Cable Installation Cable Enterprise has temporarily left the project ... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation Work on the array cable installation started. A to... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Construction update:
Monopiles: 80 installed, 80 ... Subscribers only field
Subscribers only field
Freemium Only 2013 Foundation Installation Construction update:
Monopiles: 80 installed, 80 ... Subscribers only field
Subscribers only field
Freemium Only 2012 Foundation Installation Contruction update:
Monopiles: 74 installed, 86 r... Subscribers only field
Subscribers only field
Freemium Only 2012 Foundation Installation On this day 64 monopiles have been installed and 5... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Contruction update:
Monopiles: 48 installed, 112 ... Subscribers only field
Subscribers only field
Freemium Only 2012 Foundation Installation Construction update:
Monopiles: 44 installed - 11... Subscribers only field
Subscribers only field
Freemium Only 2012 Foundation Installation Construction update:
Monopiles: 31 installed, 129... Subscribers only field
Subscribers only field
Freemium Only 2012 Met Mast/LiDAR RWE and Carbon Trust Offshore Wind Accelerator Pro... Subscribers only field Subscribers only field
Freemium Only 2012 Offshore Substation Installation of the OSPW topside began. Installati... Subscribers only field Subscribers only field
Freemium Only 2012 Export Cable Installation Installation of the first export cable is now comp... Subscribers only field Subscribers only field
Freemium Only 2012 Offshore Substation Installation of the OSPE topside began. Installati... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation The first monopile foundation was installed by the... Subscribers only field Subscribers only field
Freemium Only 2012 Export Cable Installation The installation of the first export cable is curr... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Stanislav Yudin arrived on site to begin installat... Subscribers only field Subscribers only field
Freemium Only 2012 Export Cable Installation Export cable installation started in July 2012 (or... Subscribers only field Subscribers only field
Freemium Only 2012 Offshore Substation Stanislav Yudin commenced installation of the jack... Subscribers only field Subscribers only field
Freemium Only 2012 Offshore Substation The first of two jacket foundation structures for ... Subscribers only field Subscribers only field
Freemium Only 2012 Construction - Seabed Preparation Scour protection work by the DP Fall Pipe. Vessel... Subscribers only field Subscribers only field
Freemium Only 2011 Other Onshore transformers on site - two transformers pl... Subscribers only field Subscribers only field
Freemium Only 2011 Financial Close Final Investment Decision took place around this d... Subscribers only field Subscribers only field
Freemium Only 2010 Onshore Construction Starts Onshore construction began at the end of 2010.... Subscribers only field Subscribers only field
Freemium Only 2009 Met Mast/LiDAR Installation of 100m met mast.... Subscribers only field Subscribers only field
Freemium Only 2008 Consent Authorised Approval given by government.
Principal cause for... Subscribers only field
Subscribers only field
Freemium Only 2008 Geotechnical Site Investigation Geotechnical site investigation took place by Fugr... Subscribers only field Subscribers only field
Freemium Only 2006 Met Mast/LiDAR Carl C A/S 67m Series 5-20 installed by Seacore.... Subscribers only field Subscribers only field
Freemium Only 2005 Consent Application Submitted Consent application submitted.... Subscribers only field Subscribers only field

Copyright © 4C Offshore 2019

  • ISO 14001 173953 2015 AHSO GBR UKAS 2 | 4C Offshore
  • Achilles UVDB Supply Chain Community | 4C Offshore