Subscribers only field |
Subscribers only field |
Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Performance Monitoring |
In the period of April 2014 to March 2015 the offs... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Turbine |
J/U WIND SERVER was on site supporting maintenance... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Export Cable |
The 12 meter Catamaran ‘MTS XPLORER’ undertook Geo... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
A section of export cable near turbines A06 and A0... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
The faulty section of the export cable was recover... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Turbine |
The self-propelled jack-up vessel WIND SERVER arri... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Turbine |
The maintenance work on C02, D01, B10 and A11 was ... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Foundation |
Divers will inspect the offshore substation positi... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
The vessel Stril Explorer arrived at site to re-bu... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
The vessel Deep Volans and Deep Purple began a geo... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Other |
Infield survey and turbine and foundation inspecti... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Turbine Installation |
Turbine installation was completed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
|
The Walney wind farm successfully restructured its... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Turbine |
A programme of turbine ladder cleaning maintenance... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Environmental and Seabed Monitoring |
The vessel Fugro Seeker started a seabed survey.... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Environmental and Seabed Monitoring |
Benthic survey was undertaken for approximately 6 ... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
The vessel VIDAR is expected to arrive at Liverpoo... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
|
The wind farm began producing power again after a ... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Generating Power |
34 turbines have been powered.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Export Cable Installation |
The export cable installation finished.... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Turbine |
Update - delayed, vessel arrived 20th January. MP... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Generating Power |
27 of the turbines received first power.... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Site Investigation |
The vessel PRINCE MADOG is undertaking an environm... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Site Investigation |
Geophysical surveys of the project site and the ex... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Offshore Substation |
The topside of the offshore substation was install... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
|
Ofgem accepted an Income adjustment claim from Blu... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Export Cable |
All turbines are back online following the power o... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Financing Agreement |
OPW (the PGGM and Ampere JV) refinanced its 24.8% ... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Ownership Change |
PGGM has acquired a 9.9 percent stake in the park ... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Turbine Installation |
Following a period of adverse weather conditions, ... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Array Cable Installation |
Array cable installation was well underway, with 2... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Environmental and Seabed Monitoring |
A geophysical survey is being undertaken on the ex... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Turbine |
A six week programme of leading edge blade repair ... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Export Cable |
A power outage occurred at the Walney 2 wind farm ... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
The cable was repaired and returned to the seabed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Turbine Installation |
29 wind turbine generators have been installed at ... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Array Cable Installation |
12 array cables have been installed at the site.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Array Cable Installation |
All array cables have been laid on the seabed; all... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Turbine Installation |
43 complete turbines were installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Array Cable Installation |
18 array cables have been placed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Foundation Installation |
The first transition piece was successfully loaded... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Foundation Installation |
Foundation installation got off to a good start wi... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Turbine Installation |
Eight turbines were installed at the site.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Foundation Installation |
37 monopiles and 21 transition pieces were install... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Grid Connection Agreed |
182MW of grid connection was made available by the... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Foundation |
A maintenance program involving the inspections of... Subscribers only field |
Subscribers only field
|
Freemium Only 2037 |
Turbine Service Agreement Expires |
The joint DONG Energy and Siemens team will perfor... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Fully Commissioned |
The wind farm was powering at full capacity. Walne... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Turbine |
Infield survey operations and, turbine and foundat... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Environmental and Seabed Monitoring |
Bird surveys were conducted from this date until 1... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Turbine |
The Jack-up Sea Installer arrived at Walney on 13/... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Turbine |
The maintenance work on the turbine F10 has been c... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Other |
On 9 May 2018 when during switching to release the... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
|
The MMO awarded Blue Transmission a marine licence... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Other |
A Bathymetric survey that covered all 102 turbines... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Turbine Installation |
36 SWT-3.6-120 turbines had been installed; both t... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Financing Agreement |
Statkraft signed a Power Purchase Agreement (PPA) ... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
The vessel Vidar was still jacked up at the site.... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
Unsettled weather in the area is causing delays in... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
The vessel Kingdom Of Fife arrived on site to carr... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Generating Power |
Official inauguration took place.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Foundation Installation |
The first monopile foundation was placed for Walne... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Export Cable Installation |
Installation of the export cable began around this... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable |
The vessel MERSEY GUARDIAN should begin a survey a... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Turbine |
Jack-up Pacific Osprey exchanged major components ... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Other |
The last transition piece was installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Generating Power |
All turbines were exporting power to the grid.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Foundation Installation |
The offshore substation jacket was installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Site Investigation |
Bird surveys were carried out at Ormonde and Walne... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Turbine |
Work started to exchange some major turbine compon... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Environmental and Seabed Monitoring |
Ultrabeam Limited will undertake a multibeam and s... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Export Cable |
Walney 2 suffered from a power outage at 18:00, th... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Turbine Installation |
29 SWT-3.6-120 turbineshad been installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Turbine Installation |
Both Kraken and Leviathan installed their first tu... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Foundation Installation |
The final foundation was installed. At this stage,... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Ownership Change |
SSE agreed to sell its 25.1% non-operating stake i... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Generating Power |
The first turbine started to produce power and the... Subscribers only field |
Subscribers only field
|
Freemium Only 2007 |
Consent Authorised |
Principal cause for delays in consenting: Birds (p... Subscribers only field |
Subscribers only field
|
Freemium Only 2009 |
Financial Close |
Final Investment Decision (FID) made by the DONG E... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Turbine |
J/U WIND SERVER carried out a major component exch... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Performance Monitoring |
From March 2015 to March 2016 Walney 2 OFTO only h... Subscribers only field |
Subscribers only field
|
Freemium Only 2006 |
Consent Application Submitted |
Consent application submitted.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Array Cable Installation |
Array cable installation started.... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Financing Agreement |
GIB provided £45m as part of a debt package to ref... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Other |
The onshore substation was energised.... Subscribers only field |
Subscribers only field
|