Developers/Owners/Operators (4)

RoleOrganisation 
Developer
correct
Operator
Ocean Breeze Energy GmbH & Co. KG. (HypoVereinsbank)
Ocean Breeze Energy GmbH & Co. KG is owner and operator of the windfarm, BARD Offshore 1 (BO1) - Ocean Breeze Energy GmbH & Co. KG is 100% indirectly held by UniCredit Bank AG, Munich.
correct
Operator-Offshore Transmission
EnBW Energie Baden-Württemberg AG
Client: LogIn
correct
Owner
Ocean Breeze Energy GmbH & Co. KG. (HypoVereinsbank)
correct

Turbines (9)

RoleOrganisation 
Installer(LEAD)-Turbine
Installation of 80 x Bard 5.0 turbines
Number of turbines installed: LogIn
correct
Installer-Turbine correct
Installer-Turbine correct
Installer-Turbine correct
Installer-Turbine correct
Maintenance-Turbine
Offshore Wind Solutions GmbH (Reetec GmbH)
correct
Manufacturer-Turbine
Supply of 80 x Bard 5.0 turbines
Nominal Capacity (MW): LogIn
correct
Manufacturer-Turbine(Tower)
Delivery of 47 towers
Number of towers: LogIn
correct
Manufacturer-Turbine(Tower) correct

Substations (5)

Foundations (20)

RoleOrganisation 
Contractor-Grouting(substation)
2010 - Jacket (4 legs) - Ducorit S5
Number of foundations grouted: LogIn
correct
Contractor-Grouting(turbines) correct
Designer(Detailed)-Foundation(Turbine) correct
Installer(LEAD)-Transition Piece(turbine) correct
Installer-Foundation(substation) correct
Installer-Foundation(turbine) correct
Installer-Transition Piece(turbine)
Installation of the 80 tripile foundation Transitions
Number of transition pieces installed: LogIn
correct
Maintenance-Foundations
NDE will carry out underwater inspections, service and installation as well as inspection and service of the transition pieces. The inspection campaign has taken place every year from 2011-2016.
correct
Maintenance-Foundations
NDE Offshore have a two year inspection, repair and maintenance contract. The service contract includes inspections, maintenance and installation activities as well as ICCP works. NDE Offshore, a Sweden-based provider of offshore services, will continue the successful combined topside and subsea operation using the vessel Ocean Zephyr, equipped with a Walk-to-Work system and ROV. The campaign will comprise of topside inspection, service and installation as well as underwater inspections of the transition pieces. The installation scope, is carried out from a second vessel, Glomar Wave.
correct
Manufacturer-Foundation(PinPiles)
2008-2010 - Total weight = 100000
Pile:
Diameter: 3.35m
Wall thickness: 50 - 94mm
Length: 85m
Weight: 416.66t

Number of piles manufactured: LogIn
correct
Manufacturer-Foundation(substation) correct
Manufacturer-Foundation(substation) correct
Manufacturer-Foundation(turbine)
Manufacture of 12 tripile structures
Number of foundations: LogIn
correct
Manufacturer-Foundation(turbine)
Supply of 68 tripile (204 piles) foundations
Number of foundations: LogIn
correct
Manufacturer-Foundation-Primary Steel(turbine)
Manufacture of 66 lower pins for tripiles
Number of foundations: LogIn
correct
Manufacturer-Foundation-Primary Steel(turbine) correct
Manufacturer-Transition Piece(turbine)
Supply of 80 transition pieces
Number of transition pieces: LogIn
correct
Manufacturer-Transition Piece-Primary Steel(turbine)
2008-09 - Transitions incl. Pins 5.000 x 60 x 4.000 Weight 33000t
Number of transition pieces: LogIn
correct
Manufacturer-Transition Piece-Primary Steel(turbine) correct
Manufacturer-Transition Piece-Secondary Steel(turbine) correct

Array Cabling (5)

RoleOrganisation 
Installer-Array Cabling
The contract covers the installation, trenching and connection of the array cables
Cable Length km: LogIn
correct
Installer-Array Cabling(burial)
Maersk Recorder mobilized with WROV and CMROV 4 jet trenching ROV for 112km cable lay
Cable Length km: LogIn
correct
Installer-Array Cabling(cable lay)
Maersk Recorder mobilized with WROV and CMROV 4 jet trenching ROV for 112km cable lay
Cable Length km: LogIn
correct
Manufacturer-Array Cabling
Norddeutsche Seekabelwerke GmbH & Co. KG (General Cable Nordic AS)
Client: LogIn
correct
Supplier-Cable Protection Systems correct

Export Cabling (3)

Met Masts (0)

Consultants (8)

RoleOrganisation 
Consultant-Health & Safety
Staatliches Gewerbeaufsichtsamt Oldenburg acted as the supervisory authority for the health and safety of the project. Offshore wind farms in the EEZ were assigned to the department in the year 2009 by the ministry of social affairs of lower saxony.
correct
Consultant-Other correct
Consultant-Other
Provided dive and ROV support.
correct
Consultant-Other
DHI Group
Client: LogIn
correct
Consultant-Other correct
Consultant-Other correct
Consultant-Other
From 2009 onward 8.2 Consulting provided: Technical consultancy, Inspection and analysis of WTG prototypes including boroscopy, contract negotiation assistance, inspection of all major components at quayside, construction
monitoring offshore, production monitoring of
jack-up barge, monitoring of WTG
commissioning, validation of Escrow Account
correct
Consultant-Weather Forecasting
Daily forecasts of weather and wave conditions for construction, delivered via web portal and email
correct

Others (16)

RoleOrganisation 
Contractor-Other
Norddeutsche Seekabelwerke GmbH & Co. KG (General Cable Nordic AS)
correct
Contractor-Other correct
Contractor-Other correct
Maintenance-Other
Offshore Wind Solutions GmbH (Reetec GmbH)
Client: LogIn
correct
Manufacturer-Other correct
Port
Diver-service, vessel-service
correct
Port correct
Port
Base port for the logistics and installation works during project. Providing onshore assembly area and logistic support during rotor star assembly. Handling and storage of offshore wind components on terminal. Jack-up installation barges and vessels Windlift, JB115, JB117, Thor and Brave Tern berthed at terminal
correct
Supplier-Navigation Aids
Sabik Offshore Ltd
Client: LogIn
correct
Supplier-Other correct
Supplier-Other
The Design and engineering of the CP system of all tripods structures of OWF Bard Offshore One
correct
Supplier-Other
Supplied a total of 400 foundation and tower flanges (160 x ø5500 mm, 160 x ø5000 mm, 80 x ø4700 mm) - Additional Client: Ambau
correct
Supplier-Other
Supplied the protective coating for the foundation.
correct
Supplier-Other
Supplied PPE equipment and consumables
correct
Supplier-Temporary Power
Offshore Substation - Scope of supply - Temporary power supply / Planning and delivery of generators (offshore) and other temporary power equipment.
correct
Surveyor-Geotechnical correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
1234
StatusName
Decommissioned Hooksiel Hooksiel
Fully Commissioned Alpha Ventus Alpha Ventus
Fully Commissioned Amrumbank West Amrumbank West
Fully Commissioned BARD Offshore 1 BARD Offshore 1
Fully Commissioned Borkum Riffgrund 1 Borkum Riffgrund 1
Fully Commissioned Breitling Breitling
Fully Commissioned Butendiek Butendiek
Fully Commissioned DanTysk DanTysk
Fully Commissioned EnBW Baltic 1 EnBW Baltic 1
Fully Commissioned EnBW Baltic 2 EnBW Baltic 2
Fully Commissioned ENOVA Offshore Project Ems Emden ENOVA Offshore Project Ems Emden
Fully Commissioned Global Tech I Global Tech I
Fully Commissioned Gode Wind 1 and 2 Gode Wind 1 and 2
Fully Commissioned Meerwind Süd/Ost Meerwind Süd/Ost
Fully Commissioned Nordergründe Nordergründe
Fully Commissioned Nordsee One Nordsee One
Fully Commissioned Nordsee Ost Nordsee Ost
Fully Commissioned Riffgat Riffgat
Fully Commissioned Sandbank Sandbank
Fully Commissioned Trianel Windpark Borkum I Trianel Windpark Borkum I
Fully Commissioned Veja Mate Veja Mate
Fully Commissioned Wikinger Wikinger
Under Construction Arkona Arkona
Under Construction Borkum Riffgrund 2 Borkum Riffgrund 2
Under Construction Hohe See Hohe See
Under Construction Merkur Merkur
Under Construction OWP Albatros OWP Albatros
Pre-Construction Deutsche Bucht Deutsche Bucht
Pre-Construction GICON Schwimmendes Offshore Fundament (SOF) Pilot GICON Schwimmendes Offshore Fundament (SOF) Pilot
Pre-Construction Trianel Windpark Borkum II Trianel Windpark Borkum II
Consent Authorised Arcadis Ost 1 Arcadis Ost 1
Consent Authorised Baltic Eagle Baltic Eagle
Consent Authorised Borkum Riffgrund West 2 Borkum Riffgrund West 2
Consent Authorised Borkum Riffgrund West I Borkum Riffgrund West I
Consent Authorised Deutsche Bucht Pilot Park Deutsche Bucht Pilot Park
Consent Authorised EnBW He Dreiht EnBW He Dreiht
Consent Authorised Gode Wind 3 Gode Wind 3
Consent Authorised Gode Wind 4 Gode Wind 4
Consent Authorised Kaskasi Kaskasi
Consent Authorised OWP West OWP West
Consent Authorised Wikinger Süd Wikinger Süd
Consent Application Submitted Gennaker Gennaker
Concept/Early Planning GICON® SOF 6-8MW Test Turbine GICON® SOF 6-8MW Test Turbine
Concept/Early Planning ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity) ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity)
Development Zone Darß - priority area for wind energy Darß - priority area for wind energy
Development Zone German Central Tender 2022 (Assumed North Sea) German Central Tender 2022 (Assumed North Sea)
Development Zone German Central Tender 2023 (Assumed Baltic Sea) German Central Tender 2023 (Assumed Baltic Sea)
Development Zone German Central Tender 2024 (Assumed North Sea) German Central Tender 2024 (Assumed North Sea)
Development Zone German Central Tender 2025 (Assumed North Sea) German Central Tender 2025 (Assumed North Sea)
Development Zone German Central Tender 2026 (Assumed North Sea) German Central Tender 2026 (Assumed North Sea)
1234
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/organisations.aspx?windfarmID=de23.