As an Offshore Wind Farm Subscriber, you can follow this project to add it to your dashboard.

Follow this project
Denmark 209.3MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Horns Rev 2

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Jack up vessel J/U WIND carried out maintenance wo... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine J/U WIND PIONEER arrived on site to carrying heavy... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine MPI Enterprise spent one day on site completing O&... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine J/U WIND PIONEER was on the site carrying out heav... Subscribers only field Subscribers only field
Freemium Only 2017 DONG Energy and Vattenfall secured an agreement on... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine J/U WIND was on site supporting turbine maintenanc... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine J/U WIND carried out maintenance work under the co... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine J/U WIND PIONEER along with SEA INSTALLER and SEA ... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine J/U WIND PIONEER was working on the site during th... Subscribers only field Subscribers only field
Freemium Only 2015 Performance Monitoring Horns Rev 2 has produced approximately 5.8TWh of r... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable The export cable was exporting power again. A 3.6m... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable Energinet.dk set the tentative date to begin cable... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable Energinet.dk located the fault in the export cable... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable The export cable experienced a fault stopping the ... Subscribers only field Subscribers only field
Freemium Only 2015 Met Mast/LiDAR The Mono Bucket met mast foundation was completely... Subscribers only field Subscribers only field
Freemium Only 2015 Turbine DONG will be repairing and upgrading all 273 blade... Subscribers only field Subscribers only field
Freemium Only 2015 Turbine Maintenance work took place on site supported by h... Subscribers only field Subscribers only field
Freemium Only 2015 DONG Energy inaugurated their O&M building in Esbj... Subscribers only field Subscribers only field
Freemium Only 2015 Turbine Service Agreement Expires The five-year OEM service agreement will expire du... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine J/U WIND worked on the site carrying out O&M work.... Subscribers only field Subscribers only field
Freemium Only 2014 Other Maintenance meant 0MW was being transported for a ... Subscribers only field Subscribers only field
Freemium Only 2013 Performance Monitoring During 2013 Horns Rev 2 produced 900,055MWh, or th... Subscribers only field Subscribers only field
Freemium Only 2013 Other Yearly maintenance meant 0MW was being exported fo... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine SEA ENERGY (now Excel) was used for maintenance wo... Subscribers only field Subscribers only field
Freemium Only 2012 Performance Monitoring During 2012 Horns Rev 2 produced 956,028MWh, or th... Subscribers only field Subscribers only field
Freemium Only 2012 Turbine SEA ENERGY (Excel) arrived on site to support main... Subscribers only field Subscribers only field
Freemium Only 2011 Turbine Jack up vessel SEA ENERGY (now Excel) carried out ... Subscribers only field Subscribers only field
Freemium Only 2010 Turbine J/U WIND arrived on site to support maintenance wo... Subscribers only field Subscribers only field
Freemium Only 2010 Fully Commissioned Project fully commissioned in January 2010. Horns ... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation Final turbine installed - installation is now comp... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation By mid-October, A2SEA had installed 85 of the 91 S... Subscribers only field Subscribers only field
Freemium Only 2009 Generating Power Generating power and inaugurated by HRH Crown Prin... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation By mid-September, A2SEA had installed 77 of the 91... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation By mid-August, A2SEA had installed 74 of the 91 Si... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation By mid-July, A2SEA had installed 64 of the 91 Siem... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation By mid-June, A2SEA had installed 45 of the 91 Siem... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation By mid-May, A2SEA had installed 29 of the 91 Sieme... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation By mid-April, A2SEA had installed 11 of the 91 Sie... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation First turbine installed.... Subscribers only field Subscribers only field
Freemium Only 2009 Turbine Installation A2SEA began turbine installation activities.... Subscribers only field Subscribers only field
Freemium Only 2008 Offshore Substation The substation was installed between August and Se... Subscribers only field Subscribers only field
Freemium Only 2008 Foundation Installation Foundation installation started May 2008.... Subscribers only field Subscribers only field
Freemium Only 2008 Offshore Construction Starts Offshore construction work started.... Subscribers only field Subscribers only field
Freemium Only 2007 Financial Close Shortly after April DONG Energy made the final inv... Subscribers only field Subscribers only field
Freemium Only 2007 Consent Authorised Consent was granted in March 2007.... Subscribers only field Subscribers only field
Freemium Only 2005 Consent Application Submitted Estimated date for planning consent submission.... Subscribers only field Subscribers only field
Freemium Only 2003 Financing Agreement The Environmental Investment Bank (EIB) provided u... Subscribers only field Subscribers only field

Copyright © 4C Offshore 2019