Events on Hornsea Project One

As an Offshore Wind Farm Subscriber, you can follow this project to add it to your dashboard.

Follow this project
United Kingdom 1218MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Hornsea Project One

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2021 Generating Power update 30/01/2020: Hornsea 1 will receive the CfD ... Subscribers only field Subscribers only field
Freemium Only 2021 Hornsea 1’s 18-month commissioning period ends on ... Subscribers only field Subscribers only field
Freemium Only 2020 Ownership Change Update: 19/02/2020 - Ofgem appoints Diamond Transm... Subscribers only field Subscribers only field
Freemium Only 2020 Consultation The UK government is proposing an exemption order ... Subscribers only field Subscribers only field
Freemium Only 2020 The generated revenues increased by 25% in Q1 2020... Subscribers only field Subscribers only field
Freemium Only 2020 Array Cable Cable repairs are complete.
update 30/01/2020 Cab... Subscribers only field
Subscribers only field
Freemium Only 2020 Generating Power The second phase of Hornsea 1 began recieving paym... Subscribers only field Subscribers only field
Freemium Only 2020 Generating Power update 30/01/2020: Hornsea 1 will receive the CfD ... Subscribers only field Subscribers only field
Freemium Only 2020 Hornsea One Ltd (Orsted) has agreed to pay a volun... Subscribers only field Subscribers only field
Freemium Only 2020 Tender Process Ofgem to make preferred bidder decision for the OF... Subscribers only field Subscribers only field
Freemium Only 2019 Fully Commissioned update 30/01/20: Orsted confirmed that the proejct... Subscribers only field Subscribers only field
Freemium Only 2019 Array Cable Seaway Aimery is to carry out array cable repairs ... Subscribers only field Subscribers only field
Freemium Only 2019 Site Investigation Nearshore geophysical survey works will commence w... Subscribers only field Subscribers only field
Freemium Only 2019 Other Orsted expects to resume maximum power exports (cu... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation The final SWT-7.0-154 t urbine was installed. Load... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Siemens Gamesa announced that it had installed 147... Subscribers only field Subscribers only field
Freemium Only 2019 Site Investigation Spectrum Offshore announced that it had concluded ... Subscribers only field Subscribers only field
Freemium Only 2019 Other Update January 2020: A detailed report from OFGEM ... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Bold Tern is now leaving Port of Hull with the 19t... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation 123 wind turbines have been installed. Commissioni... Subscribers only field Subscribers only field
Freemium Only 2019 Grid Connection Available National Grid will provide the final 400MW of grid... Subscribers only field Subscribers only field
Freemium Only 2019 Site Investigation Geophysical survey works with Geosurveyor XI, whic... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation The 100th turbine was installed on 4th July 2019, ... Subscribers only field Subscribers only field
Freemium Only 2019 Array Cable Installation JDR completed installation and testing of all 58 c... Subscribers only field Subscribers only field
Freemium Only 2019 Tender Process Ofgem to commence ITT stage for the OFTO tender pr... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Construction update - Bold Tern left Hull to comme... Subscribers only field Subscribers only field
Freemium Only 2019 Generating Power Update 20/06/2019: LCCC announced that the first O... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation 87 turbines have been installed and fully commissi... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation The Bold Tern has installed her 44th turbine, mark... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement Windhoist have completed pre-assembly of approxima... Subscribers only field Subscribers only field
Freemium Only 2019 Generating Power Ørsted officially commenced operations on Hornsea ... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation 68 turbines have been installed, of these the comm... Subscribers only field Subscribers only field
Freemium Only 2019 Site Investigation Geophysical survey to be carried out from 15th May... Subscribers only field Subscribers only field
Freemium Only 2019 Array Cable Installation JDR Services successfully completed the terminatio... Subscribers only field Subscribers only field
Freemium Only 2019 Array Cable Installation JDR Cables completed array cable installation with... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation 54 turbines have been installed, of these the comm... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation 51 turbines have been installed and are generating... Subscribers only field Subscribers only field
Freemium Only 2019 Foundation Installation Foundation installation was completed on 25th Apri... Subscribers only field Subscribers only field
Freemium Only 2019 Leask Marine's C-Fenna performed wave rider recove... Subscribers only field Subscribers only field
Freemium Only 2019 Tender Process Ofgem has shortlisted bidders for three offshore w... Subscribers only field Subscribers only field
Freemium Only 2019 Array Cable Installation Edda Freya finished the second installation campai... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement Update: load out is scheduled for around 5th April... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Working in tandem Fred. Olsen Windcarrier's Bold T... Subscribers only field Subscribers only field
Freemium Only 2019 Array Cable Installation 151 of 176 array cables have been installed, of wh... Subscribers only field Subscribers only field
Freemium Only 2019 Grid Connection Available National Grid will provide the second 400MW of gri... Subscribers only field Subscribers only field
Freemium Only 2019 Other Post-lay rock-placement works along the export cab... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Construction Update:
All but two monopiles and ... Subscribers only field
Subscribers only field
Freemium Only 2019 Grid Connection Available National Grid will provide the first 400MW of grid... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation SEA CHALLENGER has arrived on Horsea Project One t... Subscribers only field Subscribers only field
Freemium Only 2019 Foundation Installation 172 out of 174 monopile foundations have been inst... Subscribers only field Subscribers only field
Freemium Only 2019 Generating Power The first Siemens Gamesa SWT-7.0-154 (turbine F18)... Subscribers only field Subscribers only field
Freemium Only 2019 Tender Process Ofgem to complete the EPQ bidding and evaluation p... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement The final transition pieces manufactured by EEW SP... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Fred. Olsen Windcarrier will deploy its vessel Bol... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement EEW announced the completion of their Hornsea One ... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement Bold Tern arrived at Hull ready to start turbine i... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement Bold Tern is on her way to Hull to mobilize for th... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement The third to last load out of transition pieces sa... Subscribers only field Subscribers only field
Freemium Only 2019 Foundation Installation 165 monopiles have been installed and 152 transiti... Subscribers only field Subscribers only field
Freemium Only 2019 Met Mast/LiDAR Apollo was deployed to remove the met mast on site... Subscribers only field Subscribers only field
Freemium Only 2019 Array Cable Installation DeepOcean will begin its second array cable instal... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation Ørsted announces the completion of export cable in... Subscribers only field Subscribers only field
Freemium Only 2018 Onshore Cable Installation J Murphy & Sons have completed onshore cable inst... Subscribers only field Subscribers only field
Freemium Only 2018 Tender Process OFGEM published a notice under the electricity (co... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement EEW SPC currently producing 58 foundations for thi... Subscribers only field Subscribers only field
Freemium Only 2018 Ownership Change Ørsted completed the divestment of 50% of the Horn... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement The first turbine tower has been pre-assembled rea... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation 104 out of 174 foundations installed.... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation 66 out of 174 array cable installed.... Subscribers only field Subscribers only field
Freemium Only 2018 Health and Safety On 31/10/18, a loading incident occured during lif... Subscribers only field Subscribers only field
Freemium Only 2018 Tender Process Ofgem intends to commence tender exercises for Off... Subscribers only field Subscribers only field
Freemium Only 2018 Tender Process Offshore Transmission Owner (OFTO) Tender Round Si... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation GeoSea has installed half of the monopile foundati... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement EEW SPC deliveredthe final six monopiles to Able ... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement ALE and their Conbit reached the half-way mileston... Subscribers only field Subscribers only field
Freemium Only 2018 Other Tideway has successfully jointed a sub-sea cable i... Subscribers only field Subscribers only field
Freemium Only 2018 Ownership Change Ørsted has signed an agreement to sell 50% of the ... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement Wilton Engineering loaded out the first four trans... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation DP2 Innovation restarted foundation installation w... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation The last two topsides were installed.... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation Saipem 7000 commenced installation of the remainin... Subscribers only field Subscribers only field
Freemium Only 2018 Onshore Cable Installation In July 2018, Orsted finished Horizontal Direction... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation Over summer, the CLV Connector will be accompanied... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation Edda Freya has started array cable work on Hornsea... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation The Reactive Compensation Station (RCS) was instal... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation The central export cable has been laid and work pr... Subscribers only field Subscribers only field
Freemium Only 2018 Construction - Seabed Preparation Boulder clearance activity will commence along arr... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation 60 transition pieces have been installed by Sea Ch... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation DP2 INNOVATION and SEA INSTALLER have left the sit... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation 58 monopiles have been installed and 26 transition... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation The first offshore substation topside (Z12) has be... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation The first jacket installation was completed on Thu... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable Installation Tideway BV laid the first offshore export cable se... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement Bladt Industries commenced load out of the first o... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation Hornsea Project One commenced installation of the ... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement Load out of the four jackets for the offshore subs... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation 44 monopiles have been installed and 17 transition... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation 32 monopiles have been installed and six transitio... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation The first transition piece has been installed at t... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement The loadout of the first 6 transition pieces and a... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation Innovation joined by A2Sea’s vessel SEA INSTALLER ... Subscribers only field Subscribers only field
Freemium Only 2018 Ørsted confirmed that it is in discussions to dive... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation The first monopiles were installed by GeoSea’s ins... Subscribers only field Subscribers only field
Freemium Only 2018 Foundation Installation DP2 Innovation arrived on site on 23rd Jan 2018 r... Subscribers only field Subscribers only field
Freemium Only 2018 Other Cable Trenching works are ongoing.... Subscribers only field Subscribers only field
Freemium Only 2018 Production and Procurement Babcock are set to complete manufacture of the wor... Subscribers only field Subscribers only field
Freemium Only 2018 Financing Agreement DONG Energy expects to divest up to 50% of the pro... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement The first six monopiles were loaded at the quay in... Subscribers only field Subscribers only field
Freemium Only 2017 Construction - Seabed Preparation Pre-trenching works are ongoing within the export ... Subscribers only field Subscribers only field
Freemium Only 2017 Construction - Seabed Preparation Boulder Clearance and Scour Protection in preparat... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement Offshore Structures Britain installed the first ex... Subscribers only field Subscribers only field
Freemium Only 2017 Detonation of the final UXO.... Subscribers only field Subscribers only field
Freemium Only 2017 Construction - Seabed Preparation Boulder clearance works in the offshore export cab... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement The helideck was installed on the first of the thr... Subscribers only field Subscribers only field
Freemium Only 2017 Geotechnical Site Investigation MV Bucentaur began geotechnical investigations. T... Subscribers only field Subscribers only field
Freemium Only 2017 Site Investigation Hornsea Project One have detonated 20 of the 21 co... Subscribers only field Subscribers only field
Freemium Only 2017 Other Onshore construction for landfall is progressing a... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement DONG Energy have announced that instead of the 58 ... Subscribers only field Subscribers only field
Freemium Only 2017 Site Investigation A total of six unexploded ordnances have been iden... Subscribers only field Subscribers only field
Freemium Only 2017 Other Landfall HDD work began.... Subscribers only field Subscribers only field
Freemium Only 2017 Site Investigation The Fugro vessel Victor Hensen deployed a benthic ... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement Bladt confirmed the second offshore substation arr... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement The first substation arrived at Bladt Industries' ... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement EEW SPC began fabrication of the 116 monopile foun... Subscribers only field Subscribers only field
Freemium Only 2017 Geotechnical Site Investigation Engineering route survey will take place in 2017.... Subscribers only field Subscribers only field
Freemium Only 2016 PreTesting A trial trenching operation is scheduled to begin ... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Bladt began the construction of the offshore subst... Subscribers only field Subscribers only field
Freemium Only 2016 Onshore Cable Installation In September 2016, enabling works began for the on... Subscribers only field Subscribers only field
Freemium Only 2016 Other Approval The Planning Inspectorate published responses to t... Subscribers only field Subscribers only field
Freemium Only 2016 Other Approval Low Carbon Contracts Company (LCCC) announced that... Subscribers only field Subscribers only field
Freemium Only 2016 Other Application Submitted DONG Energy submitted a Supporting Statement to th... Subscribers only field Subscribers only field
Freemium Only 2016 Other Approval The Secretary of State granted an application for ... Subscribers only field Subscribers only field
Freemium Only 2016 Onshore Construction Starts Onshore substation construction work began and is ... Subscribers only field Subscribers only field
Freemium Only 2016 Financial Close DONG Energy made a final investment decision commi... Subscribers only field Subscribers only field
Freemium Only 2015 Other Application Submitted The Planning Inspectorate accepted changes to the ... Subscribers only field Subscribers only field
Freemium Only 2015 Geotechnical Site Investigation Fugro were contracted by DONG Energy to carry out ... Subscribers only field Subscribers only field
Freemium Only 2015 Ownership Change DONG Energy Wind Power A/S acquired the full devel... Subscribers only field Subscribers only field
Freemium Only 2014 Consent Authorised The Secretary of State for Energy and Climate Chan... Subscribers only field Subscribers only field
Freemium Only 2014 Site Investigation Geophysical survey activities started on the 1st N... Subscribers only field Subscribers only field
Freemium Only 2014 Site Investigation Geophysical surveys started at the site.... Subscribers only field Subscribers only field
Freemium Only 2014 Other Approval The National Infrastructure Planning Inspectorate ... Subscribers only field Subscribers only field
Freemium Only 2014 PreTesting A temporary trial installation and recovery of two... Subscribers only field Subscribers only field
Freemium Only 2014 Financing Agreement One of eight renewable energy projects to sign con... Subscribers only field Subscribers only field
Freemium Only 2014 Other Approval Vi Aura Limited were granted an Electricity Genera... Subscribers only field Subscribers only field
Freemium Only 2014 Subsidy/PPA Conditionally Secured Offered an early stage Contracts for Difference (C... Subscribers only field Subscribers only field
Freemium Only 2014 Other Application Submitted Applied for an electricity generation licence thro... Subscribers only field Subscribers only field
Freemium Only 2013 Other Approval DECC sent draft Investment Contracts to applicants... Subscribers only field Subscribers only field
Freemium Only 2013 Other Approval On the 04/12/2013 the Government announced the qua... Subscribers only field Subscribers only field
Freemium Only 2013 Other Approval Hornsea Project One was accepted for examination b... Subscribers only field Subscribers only field
Freemium Only 2013 Consent Application Submitted The application was made on this day and the Plann... Subscribers only field Subscribers only field
Freemium Only 2013 Site Investigation MV Neptune began conducting a geophysical survey, ... Subscribers only field Subscribers only field
Freemium Only 2013 Site Investigation SMart Wind held the final stages of consultation f... Subscribers only field Subscribers only field
Freemium Only 2012 Other Approval The project was granted its Electricity Generation... Subscribers only field Subscribers only field
Freemium Only 2012 Other Application Submitted Heron Wind Ltd submitted an application for an ele... Subscribers only field Subscribers only field
Freemium Only 2012 Geotechnical Site Investigation Geotechnical investigation started.... Subscribers only field Subscribers only field
Freemium Only 2011 Met Mast/LiDAR Met Mast Installed - Twisted jacket design concept... Subscribers only field Subscribers only field
Freemium Only 2011 Other Approval Mainstream and Siemens signed Agreements for Lease... Subscribers only field Subscribers only field
Freemium Only 2011 Geotechnical Site Investigation Geotechnical investigation took place.... Subscribers only field Subscribers only field
Freemium Only 2010 Tender Process SMart Wind has secured the grid connection for the... Subscribers only field Subscribers only field
Freemium Only 2010 Site Investigation The tenders were won and the site selection within... Subscribers only field Subscribers only field
Freemium Only 2008 Tender Process Proposals for Round 3.... Subscribers only field Subscribers only field