Germany 350MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Wikinger

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2019 As part of a migratory bird study planned by the B... Subscribers only field Subscribers only field
Freemium Only 2019 Other Approval DNV GL has issued Iberdrola with a certificate for... Subscribers only field Subscribers only field
Freemium Only 2019 Array Cable 50Hertz carried out the removal of an array cable ... Subscribers only field Subscribers only field
Freemium Only 2019 Generating Power 50Hertz completed the Ostwind 1 grid connection on... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine MPI Enterprise worked on the site during this peri... Subscribers only field Subscribers only field
Freemium Only 2018 Fully Commissioned The wind farm was inaugurated at ceremony held at... Subscribers only field Subscribers only field
Freemium Only 2018 Array Cable Installation Prysmian Group announced successful commissioning ... Subscribers only field Subscribers only field
Freemium Only 2018 Offshore Substation Installation of a new 83 tonne crane on top of the... Subscribers only field Subscribers only field
Freemium Only 2017 Generating Power Project connected to the German power grid, first ... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation Commissioning of the turbines is underway. RTS tec... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation The TSO 50Hertz is currently overseeing the final ... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation The last turbine was installed by Global Wind Serv... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation In total 30 turbines have been installed and 20 ha... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation According to Iberdrola's first quarter presentatio... Subscribers only field Subscribers only field
Freemium Only 2017 Iberdrola celebrated the opening of the Operation ... Subscribers only field Subscribers only field
Freemium Only 2017 Array Cable Installation Prysmian Group successfully completed laying of ar... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation The jack-up vessel Brave Tern has installed the fi... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation The vessel Brave Tern arrived at the Wikinger site... Subscribers only field Subscribers only field
Freemium Only 2017 Array Cable Installation The CS Sovereign left the project site marking the... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The last of 70 foundations was installed and the v... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation Assodiver's vessel CLV Atalanti completed the firs... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Nacelles and tower segments have arrived at the po... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Bladt loaded out the last one of the 41 jacket fou... Subscribers only field Subscribers only field
Freemium Only 2016 Foundation Installation Almost half of the jacket foundations have been su... Subscribers only field Subscribers only field
Freemium Only 2016 Array Cable Installation Trenching work for cable laying activities is comp... Subscribers only field Subscribers only field
Freemium Only 2016 Array Cable Installation The CS Sovereign arrived at the project site marki... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation The Cable Enterprise expected to finish installati... Subscribers only field Subscribers only field
Freemium Only 2016 Offshore Substation Seaway Heavy Lifting completed the installation of... Subscribers only field Subscribers only field
Freemium Only 2016 Offshore Substation Seaway Heavy Lifting began the installation of the... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation The vessel Cable Enterprise is installing the seco... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement The two topsides for the offshore substation set s... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement The jacket foundation left the Navantia dockyard i... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Navantia, Iberdrola and 50Hertz have hosted a deli... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Iberdrola and Navantia held a ceremony to celebrat... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement During the week starting the 18th the first jacket... Subscribers only field Subscribers only field
Freemium Only 2016 The first set of 3 jacket foundations left Bladt's... Subscribers only field Subscribers only field
Freemium Only 2016 ALE performed the first load-out in Ferrol, Spain.... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation By the end of June the vessel Cable Enterprise lai... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement Navantia prepares for load out of first batch of j... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation The first kilometres of the export cable has been ... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation The Cable Enterprise arrived at the cable route. I... Subscribers only field Subscribers only field
Freemium Only 2016 Foundation Installation The vessel Giant 7 arrived on site. The Giant 7 wi... Subscribers only field Subscribers only field
Freemium Only 2016 Iberdrola held a ceremony marking the start of the... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement First 32 piles are being loaded in Spain, prior to... Subscribers only field Subscribers only field
Freemium Only 2016 Construction - Seabed Preparation Shallow water boulder removal started in February ... Subscribers only field Subscribers only field
Freemium Only 2015 Other Approval Extension Commencement will occur.... Subscribers only field Subscribers only field
Freemium Only 2015 Production and Procurement NAVANTIA finished assembling first turbine Jacket.... Subscribers only field Subscribers only field
Freemium Only 2015 Production and Procurement Upending of first jacket foundation.... Subscribers only field Subscribers only field
Freemium Only 2015 Construction - Seabed Preparation Deepwater boulder removal started in November alon... Subscribers only field Subscribers only field
Freemium Only 2015 Production and Procurement The first offshore jacket foundation was completed... Subscribers only field Subscribers only field
Freemium Only 2015 Consent Authorised On 28 September 2015 the Federal Maritime and Hydr... Subscribers only field Subscribers only field
Freemium Only 2015 Production and Procurement The first of 82 A-frames for the jacket foundation... Subscribers only field Subscribers only field
Freemium Only 2015 Other Approval The BSH approved the last 20km of the export cable... Subscribers only field Subscribers only field
Freemium Only 2015 Other Approval 50Hertz received EEZ planning approval for Ostwind... Subscribers only field Subscribers only field
Freemium Only 2015 Production and Procurement Fabrication is underway.... Subscribers only field Subscribers only field
Freemium Only 2015 Other Approval 50Hertz received approval for the land route from ... Subscribers only field Subscribers only field
Freemium Only 2015 The pile tests were completed on schedule and the ... Subscribers only field Subscribers only field
Freemium Only 2014 Financial Close The final investment decision was given on 27th Oc... Subscribers only field Subscribers only field
Freemium Only 2014 Subsidy/PPA Conditionally Secured BNetzA released the results to their August 2014 a... Subscribers only field Subscribers only field
Freemium Only 2014 Other Phase 1 of a pile testing campaign started on this... Subscribers only field Subscribers only field
Freemium Only 2013 Geotechnical Site Investigation The geotechnical studies concluded and the results... Subscribers only field Subscribers only field
Freemium Only 2012 Geotechnical Site Investigation Geotechnical site investigation started on the sit... Subscribers only field Subscribers only field
Freemium Only 2012 Other Application Submitted EIA submitted to the BSH which covers the extended... Subscribers only field Subscribers only field
Freemium Only 2012 Site Investigation Engineering phase starts.... Subscribers only field Subscribers only field
Freemium Only 2012 Grid Connection Other Application for the grid connection was received b... Subscribers only field Subscribers only field
Freemium Only 2011 Consent Application Submitted Made first application for permits to the German F... Subscribers only field Subscribers only field
Freemium Only 2010 Strategy or Policy Development Iberdrola bought the rights from the existing owne... Subscribers only field Subscribers only field
Freemium Only 2007 Consent Authorised Approval of wind farm by Federal maritime and Hydr... Subscribers only field Subscribers only field
Freemium Only 2001 Consent Application Submitted Date of original application for consent utilising... Subscribers only field Subscribers only field